ITAC Assessment: CO0504
ITAC logo
ITAC Assessment: CO0504
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Rifle scopes, spotting scopes, binoculars, and rifle scope base attachme
NAICS
n/a
SIC 3827: Optical Instruments and Lenses
Sales Range $10
M
to 50
M
# of Employees 85
Plant Area 28,500
ft2
Annual Production 36,400
pieces
Production Hrs. Annual 4,680
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $10,246 639,440
kWh
Electricity Demand $32,550 2,510
kW-mo/yr
Electricity Fees $192 -
Natural Gas $8,640 970
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,705 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,705

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings
01 2.3191: Use demand controller or load shedder $3,040 $7,000 - $3,040
-
kW-mo/yr
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,250 $1,950 $540
32,800
kWh
$1,070
-
kW-mo/yr
$(-360.0) -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $371 - $540
32,800
kWh
$1,170
-
kW-mo/yr
$(-42.0) $(-1,297.0)
04 2.4133: Use most efficient type of electric motors $44 $44 $16
880
kWh
$28
-
kW-mo/yr
- -
TOTAL RECOMMENDED $4,705 $8,994 $1,096
66,480
kWh
$5,308
-
kW-mo/yr
$(-402.0) $(-1,297.0)
TOTAL IMPLEMENTED $4,705 $8,994 $1,096
66,480
kWh
$5,308
-
kW-mo/yr
$(-402.0) $(-1,297.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs