Assessment Year | 2002 |
---|---|
Principal Product | Injection molded plastic parts |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 60 |
Plant Area |
26,000
ft2
|
Annual Production | 3,000,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $33,259 | 1,938,056 |
kWh
|
$0.017 |
Electricity Demand | $46,444 | 4,225 |
kW-mo/yr
|
$10.99 |
Electricity Fees | $336 | - |
|
- |
Natural Gas | $6,789 | 791 |
MMBtu
|
$8.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $14,660 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,420 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,320 | $53,800 |
$4,650
291,700
kWh
|
$5,670
-
kW-mo/yr
|
- | - | |
02 | 2.3191: Use demand controller or load shedder | $2,090 | $6,200 | - |
$2,570
-
kW-mo/yr
|
$(-480.0) | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,060 | $1,050 |
$720
45,100
kWh
|
$700
-
kW-mo/yr
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $830 | - |
$600
37,600
kWh
|
$1,120
-
kW-mo/yr
|
- | $(-1,250.0) | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $360 | $30 |
$180
11,400
kWh
|
$180
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $14,660 | $61,080 |
$6,150
385,800
kWh
|
$10,240
-
kW-mo/yr
|
$(-480.0) | $(-1,250.0) | ||
TOTAL IMPLEMENTED | $1,420 | $1,080 |
$900
56,500
kWh
|
$880
-
kW-mo/yr
|
- | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs