ITAC Assessment: CO0502
ITAC logo
ITAC Assessment: CO0502
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Injection molded plastic parts
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 60
Plant Area 26,000
ft2
Annual Production 3,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $33,259 1,938,056
kWh
Electricity Demand $46,444 4,225
kW-mo/yr
Electricity Fees $336 -
Natural Gas $6,789 791
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,660 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,420

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $10,320 $53,800 $4,650
291,700
kWh
$5,670
-
kW-mo/yr
- -
02 2.3191: Use demand controller or load shedder $2,090 $6,200 - $2,570
-
kW-mo/yr
$(-480.0) -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,060 $1,050 $720
45,100
kWh
$700
-
kW-mo/yr
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $830 - $600
37,600
kWh
$1,120
-
kW-mo/yr
- $(-1,250.0)
05 2.4231: Reduce the pressure of compressed air to the minimum required $360 $30 $180
11,400
kWh
$180
-
kW-mo/yr
- -
TOTAL RECOMMENDED $14,660 $61,080 $6,150
385,800
kWh
$10,240
-
kW-mo/yr
$(-480.0) $(-1,250.0)
TOTAL IMPLEMENTED $1,420 $1,080 $900
56,500
kWh
$880
-
kW-mo/yr
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs