Assessment Year | 2001 |
---|---|
Principal Product | metal furniture |
NAICS |
n/a
|
SIC | 2522: Office Furniture, Except Wood |
Sales Range | $10 M to 50M |
# of Employees | 149 |
Plant Area |
90,000
ft2
|
Annual Production | 800,000,000
lb
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $47,711 | 2,958,785 |
kWh
|
$0.016 |
Electricity Demand | $82,073 | 6,281 |
kW-mo/yr
|
$13.07 |
Electricity Fees | $192 | - |
|
- |
Natural Gas | $114,980 | 19,471 |
MMBtu
|
$5.91 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $197,600 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3191: Use demand controller or load shedder | $8,120 | $12,000 | - |
$8,120
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.2437: Recover waste heat from equipment | $2,560 | $5,260 | - | - |
$2,560
-
MMBtu
|
- | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,240 | $220 |
$960
59,500
kWh
|
$1,060
-
kW-mo/yr
|
- | - | $(-780.0) | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $190 | - |
$1,160
72,100
kWh
|
$2,780
-
kW-mo/yr
|
- | - | $(-1,530.0) | - | $(-2,220.0) | |
05 | 3.1191: Change procedures / equipment / operating conditions | $104,330 | $20,000 | - | - | - |
$330
-
lb
|
- | - | $104,000 | |
06 | 3.5313: Increase amount of waste recovered for resale | $68,550 | $3,360 | - | - | - |
$310
-
lb
|
- | - | $68,240 | |
07 | 4.322: Eliminate old stock and modify inventory control | $12,610 | - | - | - | - | - | - | $12,610 | - | |
TOTAL RECOMMENDED | $197,600 | $40,840 |
$2,120
131,600
kWh
|
$11,960
-
kW-mo/yr
|
$2,560
-
MMBtu
|
$640
-
lb
|
$(-2,310.0) | $12,610 | $170,020 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs