ITAC Assessment: CO0478
ITAC logo
ITAC Assessment: CO0478
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product anodizing and electroplating
NAICS
n/a
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $500
k
to 1
M
# of Employees 13
Plant Area 9,850
ft2
Annual Production 120,000
pieces
Production Hrs. Annual 2,535
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $7,914 446,659
kWh
Electricity Demand $22,949 1,650
kW-mo/yr
Electricity Fees $408 -
Natural Gas $22,673 5,407
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,710 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,710

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings Increase in Production Savings
01 2.3191: Use demand controller or load shedder $2,280 $4,000 - $2,280
-
kW-mo/yr
- - - -
02 2.2511: Insulate bare equipment $1,970 $2,360 $620
37,515
kWh
$980
-
kW-mo/yr
$370
-
MMBtu
- - -
03 2.4239: Eliminate or reduce compressed air usage $1,550 $5,200 $320
19,343
kWh
$1,230
-
kW-mo/yr
- - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $510 $290 $180
10,844
kWh
$690
-
kW-mo/yr
- $(-360.0) - -
05 2.2437: Recover waste heat from equipment $400 $1,370 - - $400
-
MMBtu
- - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $280 $60 $60
3,517
kWh
$220
-
kW-mo/yr
- - - -
07 2.2136: Install / repair insulation on steam lines $240 $300 - - $240
-
MMBtu
- - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $130 - $20
879
kWh
$60
-
kW-mo/yr
- - $50 -
09 4.111: Add equipment/ operators to reduce production bottleneck $6,350 $12,000 - - - - - $6,350
TOTAL RECOMMENDED $13,710 $25,580 $1,200
72,098
kWh
$5,460
-
kW-mo/yr
$1,010
-
MMBtu
$(-360.0) $50 $6,350
TOTAL IMPLEMENTED $13,710 $25,580 $1,200
72,098
kWh
$5,460
-
kW-mo/yr
$1,010
-
MMBtu
$(-360.0) $50 $6,350
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs