Assessment Year | 2000 |
---|---|
Principal Product | aluminum sheet |
NAICS |
n/a
|
SIC | 3353: Aluminum Sheet, Plate, and Foil |
Sales Range | $50 M to 100M |
# of Employees | 200 |
Plant Area |
200,000
ft2
|
Annual Production | 43,270,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $413,362 | 34,938,160 |
kWh
|
$0.012 |
Electricity Demand | $970,899 | 6,579 |
kW-mo/yr
|
$147.58 |
Electricity Fees | $1,860 | - |
|
- |
Natural Gas | $1,765,093 | 641,512 |
MMBtu
|
$2.75 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $98,310 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $68,150 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3191: Use demand controller or load shedder | $7,380 | $20,000 | - |
$7,380
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,240 | $2,400 |
$2,410
203,986
kWh
|
$3,430
-
kW-mo/yr
|
- | - | - | - | - | $(-2,600.0) | - | - | |
03 | 2.1135: Repair furnaces and oven doors so that they seal efficiently | $2,310 | $1,000 | - | - |
$2,310
-
MMBtu
|
- | - | - | - | - | - | - | |
04 | 3.3131: Use evaporation to concentrate material | $62,600 | $18,400 | - |
$(-90.0)
-
kW-mo/yr
|
$(-6,700.0)
-
MMBtu
|
- |
$76,690
-
gal
|
- | - | $(-7,300.0) | - | - | |
05 | 3.8142: Distill contaminated solvents for reuse | $16,290 | $13,500 | - |
$(-60.0)
-
kW-mo/yr
|
- | - | - |
$2,890
-
gal
|
- | $(-2,380.0) | $15,840 | - | |
06 | 3.6112: Use filter and drying oven to reduce sludge volume | $6,490 | $41,000 | - | - |
$(-1,730.0)
-
MMBtu
|
$(-310.0)
-
Tgal
|
- | - |
$9,110
-
lb
|
- | - |
$(-580.0)
-
Tgal
|
|
TOTAL RECOMMENDED | $98,310 | $96,300 |
$2,410
203,986
kWh
|
$10,660
-
kW-mo/yr
|
$(-6,120.0)
-
MMBtu
|
$(-310.0)
-
Tgal
|
$76,690
-
gal
|
$2,890
-
gal
|
$9,110
-
lb
|
$(-12,280.0) | $15,840 |
$(-580.0)
-
Tgal
|
||
TOTAL IMPLEMENTED | $68,150 | $21,800 |
$2,410
203,986
kWh
|
$3,340
-
kW-mo/yr
|
$(-4,390.0)
-
MMBtu
|
- |
$76,690
-
gal
|
- | - | $(-9,900.0) | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs