| Assessment Year | 2000 |
|---|---|
| Principal Product | concrete pipe and ready mix concrete |
| NAICS |
n/a
|
| SIC | 3272: Concrete Products, Except Block and Brick |
| Sales Range | $10 M to 50M |
| # of Employees | 70 |
| Plant Area |
41,848
ft2
|
| Annual Production | 23,763
ton
|
| Production Hrs. Annual | 2,772
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $11,416 | 634,818 |
kWh
|
$0.018 |
| Electricity Demand | $57,409 | 4,131 |
kW-mo/yr
|
$13.90 |
| Electricity Fees | $834 | - |
|
- |
| Natural Gas | $12,455 | 2,522 |
MMBtu
|
$4.94 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $13,170 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,100 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3191: Use demand controller or load shedder | $2,490 | $5,000 | - |
$2,490
-
kW-mo/yr
|
- | - | - | - | - | |
| 02 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $1,100 | $1,000 |
$230
12,603
kWh
|
$1,370
-
kW-mo/yr
|
- | - | - | $(-500.0) | - | |
| 03 | 2.2511: Insulate bare equipment | $790 | $180 | - | - |
$790
-
MMBtu
|
- | - | - | - | |
| 04 | 2.7224: Reduce space conditioning during non-working hours | $760 | $1,490 | - | - |
$760
-
MMBtu
|
- | - | - | - | |
| 05 | 2.6218: Turn off equipment when not in use | $520 | - | - | - |
$520
-
MMBtu
|
- | - | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $30 | - |
$30
1,758
kWh
|
$110
-
kW-mo/yr
|
- | - | $(-110.0) | - | - | |
| 07 | 3.1175: Use a different or recycled raw material | $4,200 | - | - | - | - | - | - | - | $4,200 | |
| 08 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $550 | - | - | - | - |
$550
-
lb
|
- | - | - | |
| 09 | 2.8121: Apply for tax-free status for energy purchases | $2,730 | $250 | - | - | - | - | - | $2,730 | - | |
| TOTAL RECOMMENDED | $13,170 | $7,920 |
$260
14,361
kWh
|
$3,970
-
kW-mo/yr
|
$2,070
-
MMBtu
|
$550
-
lb
|
$(-110.0) | $2,230 | $4,200 | ||
| TOTAL IMPLEMENTED | $4,100 | $430 |
$30
1,758
kWh
|
$110
-
kW-mo/yr
|
$790
-
MMBtu
|
$550
-
lb
|
$(-110.0) | $2,730 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs