Assessment Year | 2000 |
---|---|
Principal Product | metal stamping, metal finishing, heat treating |
NAICS |
n/a
|
SIC | 3469: Metal Stampings, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 40 |
Plant Area |
43,000
ft2
|
Annual Production | 1,000,000
lb
|
Production Hrs. Annual | 4,264
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $74,398 | 2,541,325 |
kWh
|
$0.029 |
Electricity Demand | $58,103 | 13,728 |
kW-mo/yr
|
$4.23 |
Electricity Fees | $4,647 | - |
|
- |
Natural Gas | $20,447 | 4,584 |
MMBtu
|
$4.46 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $34,830 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,430 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $7,540 | $16,000 |
$4,890
104,045
kWh
|
$4,630
-
kW-mo/yr
|
$(-1,980.0)
-
MMBtu
|
- | - | - | - | - | |
02 | 2.3191: Use demand controller or load shedder | $5,190 | $7,500 | - |
$5,190
-
kW-mo/yr
|
- | - | - | - | - | - | |
03 | 2.4239: Eliminate or reduce compressed air usage | $4,240 | $1,210 |
$3,240
94,959
kWh
|
$1,000
-
kW-mo/yr
|
- | - | - | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,350 | $400 |
$1,630
47,773
kWh
|
$500
-
kW-mo/yr
|
- | - | - | $(-780.0) | - | - | |
05 | 2.7111: Reduce illumination to minimum necessary levels | $750 | $350 |
$480
12,309
kWh
|
$270
-
kW-mo/yr
|
- | - | - | - | - | - | |
06 | 3.4156: Use flow control valves on equipment to optimize water use | $4,090 | $7,960 | - | - | - |
$1,310
-
Tgal
|
- | - | - | $2,780 | |
07 | 3.6192: Use a less expensive method of waste removal | $280 | - | - | - | - | - |
$280
-
lb
|
- | - | - | |
08 | 4.623: Employ modular jigs to reduce process set-up time | $6,930 | $6,000 | - | - | - | - | - | $6,930 | - | - | |
09 | 2.8121: Apply for tax-free status for energy purchases | $4,460 | $250 | - | - | - | - | - | - | $4,460 | - | |
TOTAL RECOMMENDED | $34,830 | $39,670 |
$10,240
259,086
kWh
|
$11,590
-
kW-mo/yr
|
$(-1,980.0)
-
MMBtu
|
$1,310
-
Tgal
|
$280
-
lb
|
$6,150 | $4,460 | $2,780 | ||
TOTAL IMPLEMENTED | $10,430 | $9,920 |
$5,350
155,041
kWh
|
$1,770
-
kW-mo/yr
|
- |
$1,310
-
Tgal
|
- | $(-780.0) | - | $2,780 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs