| Assessment Year | 2000 |
|---|---|
| Principal Product | fuser rollers and parts |
| NAICS |
n/a
|
| SIC | 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
52,000
ft2
|
| Annual Production | 1,500,000
pieces
|
| Production Hrs. Annual | 8,112
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $122,748 | 4,611,665 |
kWh
|
$0.027 |
| Electricity Demand | $73,431 | 18,213 |
kW-mo/yr
|
$4.03 |
| Electricity Fees | $4,380 | - |
|
- |
| Natural Gas | $12,615 | 3,022 |
MMBtu
|
$4.17 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $34,680 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,670 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $7,950 | $660 |
$7,950
355,217
kWh
|
- | - | - | - | - | - | - | |
| 02 | 2.3191: Use demand controller or load shedder | $6,550 | $7,500 | - |
$6,550
-
kW-mo/yr
|
- | - | - | - | - | - | |
| 03 | 2.3212: Optimize plant power factor | $6,420 | $15,880 | - |
$6,420
-
kW-mo/yr
|
- | - | - | - | - | - | |
| 04 | 2.4239: Eliminate or reduce compressed air usage | $3,670 | $1,130 |
$2,530
78,839
kWh
|
$1,140
-
kW-mo/yr
|
- | - | - | - | - | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,650 | $2,070 |
$2,530
82,356
kWh
|
$900
-
kW-mo/yr
|
- | - | - | $(-780.0) | - | - | |
| 06 | 2.7135: Install occupancy sensors | $440 | $560 |
$340
10,551
kWh
|
$100
-
kW-mo/yr
|
- | - | - | - | - | - | |
| 07 | 2.2511: Insulate bare equipment | $350 | $80 |
$270
8,206
kWh
|
$80
-
kW-mo/yr
|
- | - | - | - | - | - | |
| 08 | 3.4114: Replace city water with recycled water via cooling tower | $3,070 | $9,130 |
$(-120.0)
(-3,810)
kWh
|
$(-40.0)
-
kW-mo/yr
|
$1,040
-
Tgal
|
- | - | - | - |
$2,190
-
Tgal
|
|
| 09 | 3.3122: Use filtration, centrifuging to remove contaminants | $2,980 | - | - | - | - |
$(-500.0)
-
gal
|
- | $360 | $3,120 | - | |
| 10 | 3.6192: Use a less expensive method of waste removal | $600 | - | - | - | - | - |
$650
-
lb
|
- | $(-50.0) | - | |
| TOTAL RECOMMENDED | $34,680 | $37,010 |
$13,500
531,359
kWh
|
$15,150
-
kW-mo/yr
|
$1,040
-
Tgal
|
$(-500.0)
-
gal
|
$650
-
lb
|
$(-420.0) | $3,070 |
$2,190
-
Tgal
|
||
| TOTAL IMPLEMENTED | $9,670 | $17,950 |
$2,530
82,356
kWh
|
$7,320
-
kW-mo/yr
|
- | - |
$650
-
lb
|
$(-780.0) | $(-50.0) | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs