Assessment Year | 2000 |
---|---|
Principal Product | custom protective foam packaging |
NAICS |
n/a
|
SIC | 3086: Plastics Foam Products |
Sales Range | $5 M to 10M |
# of Employees | 50 |
Plant Area |
60,000
ft2
|
Annual Production | 2,340,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $86,010 | 2,837,046 |
kWh
|
$0.030 |
Electricity Demand | $54,744 | 12,307 |
kW-mo/yr
|
$4.45 |
Electricity Fees | $5,271 | - |
|
- |
Natural Gas | $224,531 | 55,614 |
MMBtu
|
$4.04 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $462,550 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $5,620 | $15,400 | n/a | - |
$5,620
-
kW-mo/yr
|
- | - | - | - | - | - | - |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,920 | $470 | n/a |
$4,110
106,975
kWh
|
$1,590
-
kW-mo/yr
|
- | - | - | $(-780.0) | - | - | - |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,910 | $4,030 | n/a |
$630
16,413
kWh
|
$1,280
-
kW-mo/yr
|
- | - | - | - | - | - | - |
04 | 2.1213: Direct warmest air to combustion intake | $930 | $1,400 | n/a | - | - |
$930
-
MMBtu
|
- | - | - | - | - | - |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $320 | - | n/a |
$470
12,309
kWh
|
$180
-
kW-mo/yr
|
- | - | - | - | - | $(-330.0) | - |
06 | 3.5314: Use in-process recycling whenever possible | $407,670 | $10,000 | n/a |
$(-7,160.0)
(-186,694)
kWh
|
$(-2,770.0)
-
kW-mo/yr
|
- |
$105,600
-
lb
|
- | - | - | $312,000 | - |
07 | 3.6192: Use a less expensive method of waste removal | $130 | - | n/a | - | - | - | - |
$140
-
lb
|
- | - | $(-10.0) | - |
08 | 4.621: Use fixtures to reduce machine changeout times | $31,200 | $25,000 | n/a | - | - | - | - | - | - | - | - | $31,200 |
09 | 2.8121: Apply for tax-free status for energy purchases | $9,850 | $250 | n/a | - | - | - | - | - | - | $9,850 | - | - |
TOTAL RECOMMENDED | $462,550 | $56,550 |
$(-1,950.0)
(-50,997)
kWh
|
$5,900
-
kW-mo/yr
|
$930
-
MMBtu
|
$105,600
-
lb
|
$140
-
lb
|
$(-780.0) | $9,850 | $311,660 | $31,200 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs