ITAC Assessment: CO0451
ITAC logo
ITAC Assessment: CO0451
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product animal feed
NAICS
n/a
SIC 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats
Sales Range $5
M
to 10
M
# of Employees 5
Plant Area 14,000
ft2
Annual Production 13,800
ton
Production Hrs. Annual 2,600
hrs
Location (State) Nebraska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $15,526 556,858
kWh
Electricity Demand $44,660 5,700
kW-mo/yr
Electricity Fees $135 -
Natural Gas $20,478 4,404
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,700 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,490

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.2136: Install / repair insulation on steam lines $7,190 $6,250 - - $7,190
-
MMBtu
- -
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $4,080 $4,000 - $4,080
-
kW-mo/yr
- - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $220 $20 $100
3,517
kWh
$120
-
kW-mo/yr
- - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $190 $320 $310
5,569
kWh
$400
-
kW-mo/yr
- $(-520.0) -
05 2.4133: Use most efficient type of electric motors $20 - $60
2,052
kWh
$70
-
kW-mo/yr
- - $(-110.0)
TOTAL RECOMMENDED $11,700 $10,590 $470
11,138
kWh
$4,670
-
kW-mo/yr
$7,190
-
MMBtu
$(-520.0) $(-110.0)
TOTAL IMPLEMENTED $4,490 $4,340 $410
9,086
kWh
$4,600
-
kW-mo/yr
- $(-520.0) -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs