ITAC Assessment: CO0438
ITAC logo
ITAC Assessment: CO0438
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product thermoformed plastic parts
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 60
Plant Area 33,000
ft2
Annual Production 1,000,000
pieces
Production Hrs. Annual 4,160
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $23,506 1,360,492
kWh
Electricity Demand $85,618 6,645
kW-mo/yr
Electricity Fees $780 -
Natural Gas $8,929 2,058
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $354,558 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,150

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Primary Product Savings Increase in Production Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,090 $100 $1,130
66,823
kWh
$2,520
-
kW-mo/yr
- - $(-1,560.0) - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $60 $482 $70
3,810
kWh
$160
-
kW-mo/yr
- - - $(-170.0) - -
03 3.6192: Use a less expensive method of waste removal $388 - - - - $460
-
lb
- $(-72.0) - -
04 3.5315: Lease / purchase baler; sell cardboard to recycler $260 - - - $260
-
lb
- - - - -
05 4.111: Add equipment/ operators to reduce production bottleneck $330,000 $740,000 - - - - $(-150,000.0) - - $480,000
06 4.311: Schedule deliveries according to demand $21,760 $20,000 - - - - - - $21,760 -
TOTAL RECOMMENDED $354,558 $760,582 $1,200
70,633
kWh
$2,680
-
kW-mo/yr
$260
-
lb
$460
-
lb
$(-151,560.0) $(-242.0) $21,760 $480,000
TOTAL IMPLEMENTED $2,150 $582 $1,200
70,633
kWh
$2,680
-
kW-mo/yr
- - $(-1,560.0) $(-170.0) - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Primary Product Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs