ITAC Assessment: CO0434
ITAC logo
ITAC Assessment: CO0434
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product IV transfusion apparatus and disposable plastic components
NAICS
n/a
SIC 3842: Orthopedic, Prosthetic, and Surgical Appliances and Supplies
Sales Range $10
M
to 50
M
# of Employees 190
Plant Area 54,580
ft2
Annual Production 40,000,000
pieces
Production Hrs. Annual 4,420
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $14,229 793,962
kWh
Electricity Demand $26,934 1,966
kW-mo/yr
Electricity Fees $204 -
Natural Gas $10,044 2,291
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $104,810 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Primary Product Savings
01 2.7221: Lower temperature during the winter season and vice-versa $1,340 $100 n/a $10
293
kWh
- $1,330
-
MMBtu
- - - -
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $490 $710 n/a $90
4,982
kWh
$490
-
kW-mo/yr
$(-90.0)
-
MMBtu
- - - -
03 2.7224: Reduce space conditioning during non-working hours $480 $1,400 n/a $20
1,172
kWh
- $460
-
MMBtu
- - - -
04 3.6192: Use a less expensive method of waste removal $380 $60 n/a - - - $440
-
lb
- $(-60.0) -
05 3.1163: Use plastic pallets instead of wood $230 $610 n/a - - - - - $230 -
06 4.111: Add equipment/ operators to reduce production bottleneck $96,720 $20,000 n/a - - - - - - $96,720
07 4.111: Add equipment/ operators to reduce production bottleneck $5,170 $10,000 n/a - - - - $5,170 - -
TOTAL RECOMMENDED $104,810 $32,880 $120
6,447
kWh
$490
-
kW-mo/yr
$1,700
-
MMBtu
$440
-
lb
$5,170 $170 $96,720
TOTAL IMPLEMENTED - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs