Assessment Year | 1999 |
---|---|
Principal Product | IV transfusion apparatus and disposable plastic components |
NAICS |
n/a
|
SIC | 3842: Orthopedic, Prosthetic, and Surgical Appliances and Supplies |
Sales Range | $10 M to 50M |
# of Employees | 190 |
Plant Area |
54,580
ft2
|
Annual Production | 40,000,000
pieces
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $14,229 | 793,962 |
kWh
|
$0.018 |
Electricity Demand | $26,934 | 1,966 |
kW-mo/yr
|
$13.70 |
Electricity Fees | $204 | - |
|
- |
Natural Gas | $10,044 | 2,291 |
MMBtu
|
$4.38 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $104,810 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7221: Lower temperature during the winter season and vice-versa | $1,340 | $100 | n/a |
$10
293
kWh
|
- |
$1,330
-
MMBtu
|
- | - | - | - |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $490 | $710 | n/a |
$90
4,982
kWh
|
$490
-
kW-mo/yr
|
$(-90.0)
-
MMBtu
|
- | - | - | - |
03 | 2.7224: Reduce space conditioning during non-working hours | $480 | $1,400 | n/a |
$20
1,172
kWh
|
- |
$460
-
MMBtu
|
- | - | - | - |
04 | 3.6192: Use a less expensive method of waste removal | $380 | $60 | n/a | - | - | - |
$440
-
lb
|
- | $(-60.0) | - |
05 | 3.1163: Use plastic pallets instead of wood | $230 | $610 | n/a | - | - | - | - | - | $230 | - |
06 | 4.111: Add equipment/ operators to reduce production bottleneck | $96,720 | $20,000 | n/a | - | - | - | - | - | - | $96,720 |
07 | 4.111: Add equipment/ operators to reduce production bottleneck | $5,170 | $10,000 | n/a | - | - | - | - | $5,170 | - | - |
TOTAL RECOMMENDED | $104,810 | $32,880 |
$120
6,447
kWh
|
$490
-
kW-mo/yr
|
$1,700
-
MMBtu
|
$440
-
lb
|
$5,170 | $170 | $96,720 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs