ITAC Assessment: CO0426
ITAC logo
ITAC Assessment: CO0426
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product asphalt
NAICS
n/a
SIC 2951: Asphalt Paving Mixtures and Blocks
Sales Range $10
M
to 50
M
# of Employees 320
Plant Area 30,000
ft2
Annual Production 500,000
ton
Production Hrs. Annual 5,200
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,160 2,146,249
kWh
Electricity Demand $74,280 7,359
kW-mo/yr
Electricity Fees $(-255.0) -
Natural Gas $226,903 80,853
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $201,620 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $116,150

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings Water Consumption Savings Primary Product Savings
01 2.2414: Use waste heat from hot flue gases to preheat $8,960 $5,700 $(-530.0)
(-29,601)
kWh
$(-870.0)
-
kW-mo/yr
$10,360
-
MMBtu
- - - - -
02 2.2136: Install / repair insulation on steam lines $7,390 $9,870 $3,540
196,659
kWh
$3,850
-
kW-mo/yr
- - - - - -
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $9,590 $25,000 $5,450
303,048
kWh
$4,140
-
kW-mo/yr
- - - - - -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,420 $4,303 $720
39,859
kWh
$1,700
-
kW-mo/yr
- - - - - -
05 3.2123: Convert to high volume low pressure (hvlp) paint guns $2,770 $500 - - - - - $2,770 - -
06 3.8132: Use less toxic and volatile solvent substitutes $2,380 $6,000 $(-470.0)
(-26,377)
kWh
$(-390.0)
-
kW-mo/yr
- $5,160
-
gal
- $(-1,920.0) - -
07 3.6124: Burn waste oil for heat $1,620 $5,420 - - $1,180
-
MMBtu
$440
-
gal
- - - -
08 3.3122: Use filtration, centrifuging to remove contaminants $92,990 $250,000 - - - - $15,050
-
lb
- $16,690
-
Tgal
$61,250
09 4.121: Maintain clean conditions before painting $73,500 $200,000 - - - - - - - $73,500
TOTAL RECOMMENDED $201,620 $506,793 $8,710
483,588
kWh
$8,430
-
kW-mo/yr
$11,540
-
MMBtu
$5,600
-
gal
$15,050
-
lb
$850 $16,690
-
Tgal
$134,750
TOTAL IMPLEMENTED $116,150 $275,793 $3,730
206,917
kWh
$4,680
-
kW-mo/yr
$11,540
-
MMBtu
$440
-
gal
$15,050
-
lb
$2,770 $16,690
-
Tgal
$61,250
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings Water Consumption Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs