Assessment Year | 1998 |
---|---|
Principal Product | asphalt |
NAICS |
n/a
|
SIC | 2951: Asphalt Paving Mixtures and Blocks |
Sales Range | $10 M to 50M |
# of Employees | 320 |
Plant Area |
30,000
ft2
|
Annual Production | 500,000
ton
|
Production Hrs. Annual | 5,200
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $38,160 | 2,146,249 |
kWh
|
$0.018 |
Electricity Demand | $74,280 | 7,359 |
kW-mo/yr
|
$10.09 |
Electricity Fees | $(-255.0) | - |
|
- |
Natural Gas | $226,903 | 80,853 |
MMBtu
|
$2.81 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $201,620 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $116,150 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | Water Consumption Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $8,960 | $5,700 |
$(-530.0)
(-29,601)
kWh
|
$(-870.0)
-
kW-mo/yr
|
$10,360
-
MMBtu
|
- | - | - | - | - | |
02 | 2.2136: Install / repair insulation on steam lines | $7,390 | $9,870 |
$3,540
196,659
kWh
|
$3,850
-
kW-mo/yr
|
- | - | - | - | - | - | |
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $9,590 | $25,000 |
$5,450
303,048
kWh
|
$4,140
-
kW-mo/yr
|
- | - | - | - | - | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,420 | $4,303 |
$720
39,859
kWh
|
$1,700
-
kW-mo/yr
|
- | - | - | - | - | - | |
05 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $2,770 | $500 | - | - | - | - | - | $2,770 | - | - | |
06 | 3.8132: Use less toxic and volatile solvent substitutes | $2,380 | $6,000 |
$(-470.0)
(-26,377)
kWh
|
$(-390.0)
-
kW-mo/yr
|
- |
$5,160
-
gal
|
- | $(-1,920.0) | - | - | |
07 | 3.6124: Burn waste oil for heat | $1,620 | $5,420 | - | - |
$1,180
-
MMBtu
|
$440
-
gal
|
- | - | - | - | |
08 | 3.3122: Use filtration, centrifuging to remove contaminants | $92,990 | $250,000 | - | - | - | - |
$15,050
-
lb
|
- |
$16,690
-
Tgal
|
$61,250 | |
09 | 4.121: Maintain clean conditions before painting | $73,500 | $200,000 | - | - | - | - | - | - | - | $73,500 | |
TOTAL RECOMMENDED | $201,620 | $506,793 |
$8,710
483,588
kWh
|
$8,430
-
kW-mo/yr
|
$11,540
-
MMBtu
|
$5,600
-
gal
|
$15,050
-
lb
|
$850 |
$16,690
-
Tgal
|
$134,750 | ||
TOTAL IMPLEMENTED | $116,150 | $275,793 |
$3,730
206,917
kWh
|
$4,680
-
kW-mo/yr
|
$11,540
-
MMBtu
|
$440
-
gal
|
$15,050
-
lb
|
$2,770 |
$16,690
-
Tgal
|
$61,250 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | Water Consumption Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs