Assessment Year | 1998 |
---|---|
Principal Product | metal building components |
NAICS |
n/a
|
SIC | 3448: Prefabricated Metal Buildings and Components |
Sales Range | $10 M to 50M |
# of Employees | 45 |
Plant Area |
106,800
ft2
|
Annual Production | 21,000,000
lb
|
Production Hrs. Annual | 3,250
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $32,076 | 1,003,224 |
kWh
|
$0.032 |
Electricity Demand | $26,889 | 2,731 |
kW-mo/yr
|
$9.85 |
Electricity Fees | $132 | - |
|
- |
Natural Gas | $12,717 | 2,394 |
MMBtu
|
$5.31 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $53,737 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $382 | $650 | n/a |
$167
5,275
kWh
|
$215
-
kW-mo/yr
|
- | - | - |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $500 | $270 | n/a |
$250
7,620
kWh
|
$250
-
kW-mo/yr
|
- | - | - |
03 | 2.4133: Use most efficient type of electric motors | $65 | $233 | n/a |
$24
879
kWh
|
$41
-
kW-mo/yr
|
- | - | - |
04 | 3.6192: Use a less expensive method of waste removal | $260 | - | n/a | - | - |
$260
-
lb
|
- | - |
05 | 4.111: Add equipment/ operators to reduce production bottleneck | $48,200 | - | n/a | - | - | - | $(-29,200.0) | $77,400 |
06 | 4.111: Add equipment/ operators to reduce production bottleneck | $3,020 | - | n/a | - | - | - | $3,020 | - |
07 | 4.111: Add equipment/ operators to reduce production bottleneck | $1,310 | - | n/a | - | - | - | $1,310 | - |
TOTAL RECOMMENDED | $53,737 | $1,153 |
$441
13,774
kWh
|
$506
-
kW-mo/yr
|
$260
-
lb
|
$(-24,870.0) | $77,400 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs