ITAC Assessment: CO0413
ITAC logo
ITAC Assessment: CO0413
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product metal building components
NAICS
n/a
SIC 3448: Prefabricated Metal Buildings and Components
Sales Range $10
M
to 50
M
# of Employees 45
Plant Area 106,800
ft2
Annual Production 21,000,000
lb
Production Hrs. Annual 3,250
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $32,076 1,003,224
kWh
Electricity Demand $26,889 2,731
kW-mo/yr
Electricity Fees $132 -
Natural Gas $12,717 2,394
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $53,737 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (haz) Savings Personnel Changes Savings Primary Product Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $382 $650 n/a $167
5,275
kWh
$215
-
kW-mo/yr
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $500 $270 n/a $250
7,620
kWh
$250
-
kW-mo/yr
- - -
03 2.4133: Use most efficient type of electric motors $65 $233 n/a $24
879
kWh
$41
-
kW-mo/yr
- - -
04 3.6192: Use a less expensive method of waste removal $260 - n/a - - $260
-
lb
- -
05 4.111: Add equipment/ operators to reduce production bottleneck $48,200 - n/a - - - $(-29,200.0) $77,400
06 4.111: Add equipment/ operators to reduce production bottleneck $3,020 - n/a - - - $3,020 -
07 4.111: Add equipment/ operators to reduce production bottleneck $1,310 - n/a - - - $1,310 -
TOTAL RECOMMENDED $53,737 $1,153 $441
13,774
kWh
$506
-
kW-mo/yr
$260
-
lb
$(-24,870.0) $77,400
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (haz) Savings Personnel Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs