| Assessment Year | 1997 |
|---|---|
| Principal Product | commercial printing |
| NAICS |
n/a
|
| SIC | 2752: Commercial Printing, Lithographic |
| Sales Range | $5 M to 10M |
| # of Employees | 68 |
| Plant Area |
25,000
ft2
|
| Annual Production | 1,500,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $19,180 | 1,058,910 |
kWh
|
$0.018 |
| Electricity Demand | $53,354 | 3,745 |
kW-mo/yr
|
$14.25 |
| Electricity Fees | $293 | - |
|
- |
| Natural Gas | $17,176 | 4,531 |
MMBtu
|
$3.79 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $65,365 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7124: Make a practice of turning off lights when not needed | $780 | - |
$780
43,376
kWh
|
- | - | - | - | - | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $165 | $96 |
$76
4,103
kWh
|
$89
-
kW-mo/yr
|
- | - | - | - | - | - | |
| 03 | 3.5121: Recycle waste ink and cleanup solvent | $17,160 | - | - | - |
$1,440
-
gal
|
- | - | - | $15,720 | - | |
| 04 | 3.5313: Increase amount of waste recovered for resale | $12,780 | $1,800 | - | - | - |
$12,780
-
lb
|
- | - | - | - | |
| 05 | 3.6192: Use a less expensive method of waste removal | $480 | - | - | - | - | - |
$480
-
lb
|
- | - | - | |
| 06 | 4.122: Develop standard procedures to improve internal yields | $34,000 | $12,680 | - | - | - | - | - | $(-50,000.0) | - | $84,000 | |
| TOTAL RECOMMENDED | $65,365 | $14,576 |
$856
47,479
kWh
|
$89
-
kW-mo/yr
|
$1,440
-
gal
|
$12,780
-
lb
|
$480
-
lb
|
$(-50,000.0) | $15,720 | $84,000 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs