ITAC Assessment: CO0401
ITAC logo
ITAC Assessment: CO0401
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product commercial printing
NAICS
n/a
SIC 2752: Commercial Printing, Lithographic
Sales Range $5
M
to 10
M
# of Employees 68
Plant Area 25,000
ft2
Annual Production 1,500,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $19,180 1,058,910
kWh
Electricity Demand $53,354 3,745
kW-mo/yr
Electricity Fees $293 -
Natural Gas $17,176 4,531
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $65,365 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Primary Product Savings
01 2.7124: Make a practice of turning off lights when not needed $780 - $780
43,376
kWh
- - - - - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $165 $96 $76
4,103
kWh
$89
-
kW-mo/yr
- - - - - -
03 3.5121: Recycle waste ink and cleanup solvent $17,160 - - - $1,440
-
gal
- - - $15,720 -
04 3.5313: Increase amount of waste recovered for resale $12,780 $1,800 - - - $12,780
-
lb
- - - -
05 3.6192: Use a less expensive method of waste removal $480 - - - - - $480
-
lb
- - -
06 4.122: Develop standard procedures to improve internal yields $34,000 $12,680 - - - - - $(-50,000.0) - $84,000
TOTAL RECOMMENDED $65,365 $14,576 $856
47,479
kWh
$89
-
kW-mo/yr
$1,440
-
gal
$12,780
-
lb
$480
-
lb
$(-50,000.0) $15,720 $84,000
TOTAL IMPLEMENTED - - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs