Assessment Year | 1997 |
---|---|
Principal Product | commercial printing |
NAICS |
n/a
|
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $5 M to 10M |
# of Employees | 68 |
Plant Area |
25,000
ft2
|
Annual Production | 1,500,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $19,180 | 1,058,910 |
kWh
|
$0.018 |
Electricity Demand | $53,354 | 3,745 |
kW-mo/yr
|
$14.25 |
Electricity Fees | $293 | - |
|
- |
Natural Gas | $17,176 | 4,531 |
MMBtu
|
$3.79 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $65,365 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7124: Make a practice of turning off lights when not needed | $780 | - |
$780
43,376
kWh
|
- | - | - | - | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $165 | $96 |
$76
4,103
kWh
|
$89
-
kW-mo/yr
|
- | - | - | - | - | - | |
03 | 3.5121: Recycle waste ink and cleanup solvent | $17,160 | - | - | - |
$1,440
-
gal
|
- | - | - | $15,720 | - | |
04 | 3.5313: Increase amount of waste recovered for resale | $12,780 | $1,800 | - | - | - |
$12,780
-
lb
|
- | - | - | - | |
05 | 3.6192: Use a less expensive method of waste removal | $480 | - | - | - | - | - |
$480
-
lb
|
- | - | - | |
06 | 4.122: Develop standard procedures to improve internal yields | $34,000 | $12,680 | - | - | - | - | - | $(-50,000.0) | - | $84,000 | |
TOTAL RECOMMENDED | $65,365 | $14,576 |
$856
47,479
kWh
|
$89
-
kW-mo/yr
|
$1,440
-
gal
|
$12,780
-
lb
|
$480
-
lb
|
$(-50,000.0) | $15,720 | $84,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs