Assessment Year | 1997 |
---|---|
Principal Product | vitamins and nutritional supplements |
NAICS |
n/a
|
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $50 M to 100M |
# of Employees | 80 |
Plant Area |
49,000
ft2
|
Annual Production | 4,500,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $13,963 | 792,790 |
kWh
|
$0.018 |
Electricity Demand | $18,334 | 1,728 |
kW-mo/yr
|
$10.61 |
Electricity Fees | $84 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $76,429 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,070 | $4,710 |
$700
47,186
kWh
|
$1,370
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $59 | $125 |
$30
2,052
kWh
|
$29
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $4,370 | $11,080 | - | - |
$4,490
-
lb
|
- | $(-120.0) | - | - | |
04 | 3.6192: Use a less expensive method of waste removal | $530 | - | - | - | - |
$530
-
lb
|
- | - | - | |
05 | 4.321: Optimize production lot sizes and inventories | $41,400 | $250,000 | - | - | - | - | - | $3,600 | $37,800 | |
06 | 4.431: Train operators for maximum operating efficiency | $28,000 | $6,280 | - | - | - | - | - | - | $28,000 | |
TOTAL RECOMMENDED | $76,429 | $272,195 |
$730
49,238
kWh
|
$1,399
-
kW-mo/yr
|
$4,490
-
lb
|
$530
-
lb
|
$(-120.0) | $3,600 | $65,800 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs