| Assessment Year | 1996 |
|---|---|
| Principal Product | refurbished folding carton machinery |
| NAICS |
n/a
|
| SIC | 3554: Paper Industries Machinery |
| Sales Range | $1 M to 5M |
| # of Employees | 80 |
| Plant Area |
32,000
ft2
|
| Annual Production | 72,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $19,064 | 598,769 |
kWh
|
$0.032 |
| Electricity Demand | $15,784 | 1,570 |
kW-mo/yr
|
$10.05 |
| Electricity Fees | $(-459.0) | - |
|
- |
| Natural Gas | $6,056 | 1,728 |
MMBtu
|
$3.50 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $32,059 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $859 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $21,800 | $14,040 |
$3,080
96,717
kWh
|
- | - | - | - | $18,720 | |
| 02 | 3.8132: Use less toxic and volatile solvent substitutes | $4,360 | $1,560 | - | - |
$4,800
-
gal
|
- | $(-440.0) | - | |
| 03 | 3.8125: Remove rollers from the machines and clean in a closed solvent cleaner | $2,730 | $1,350 | - | - | - | $1,300 | $1,430 | - | |
| 04 | 3.5146: Utilize a central coolant system for cleaning and reuse of metal working fluid | $2,310 | $11,720 | - | - |
$250
-
gal
|
- | $2,060 | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $554 | $2,458 |
$263
8,206
kWh
|
$291
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 2.4133: Use most efficient type of electric motors | $85 | $83 |
$61
2,052
kWh
|
$24
-
kW-mo/yr
|
- | - | - | - | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $220 | $180 |
$140
4,396
kWh
|
$80
-
kW-mo/yr
|
- | - | - | - | |
| TOTAL RECOMMENDED | $32,059 | $31,391 |
$3,544
111,371
kWh
|
$395
-
kW-mo/yr
|
$5,050
-
gal
|
$1,300 | $3,050 | $18,720 | ||
| TOTAL IMPLEMENTED | $859 | $2,721 |
$464
14,654
kWh
|
$395
-
kW-mo/yr
|
- | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs