Assessment Year | 1995 |
---|---|
Principal Product | Clay Brick and Tile |
NAICS |
n/a
|
SIC | 3251: Brick and Structural Clay Tile |
Sales Range | $5 M to 10M |
# of Employees | 60 |
Plant Area |
74,000
ft2
|
Annual Production | 23,000,000
pieces
|
Production Hrs. Annual | 2,652
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $134,133 | 2,202,227 |
kWh
|
$0.061 |
Natural Gas | $418,858 | 145,000 |
MMBtu
|
$2.89 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,880 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,490 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $4,250 | $11,610 |
$4,250
71,805
kWh
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,930 | $10,500 |
$4,930
102,872
kWh
|
- | |
03 | 2.2437: Recover waste heat from equipment | $2,390 | $1,710 | - |
$2,390
-
MMBtu
|
|
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $310 | $240 |
$310
4,689
kWh
|
- | |
TOTAL RECOMMENDED | $11,880 | $24,060 |
$9,490
179,366
kWh
|
$2,390
-
MMBtu
|
||
TOTAL IMPLEMENTED | $9,490 | $22,350 |
$9,490
179,366
kWh
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs