ITAC Assessment: CO0328
ITAC logo
ITAC Assessment: CO0328
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Clay Brick and Tile
NAICS
n/a
SIC 3251: Brick and Structural Clay Tile
Sales Range $5
M
to 10
M
# of Employees 60
Plant Area 74,000
ft2
Annual Production 23,000,000
pieces
Production Hrs. Annual 2,652
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $134,133 2,202,227
kWh
Natural Gas $418,858 145,000
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,880 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,490

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4133: Use most efficient type of electric motors $4,250 $11,610 $4,250
71,805
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,930 $10,500 $4,930
102,872
kWh
-
03 2.2437: Recover waste heat from equipment $2,390 $1,710 - $2,390
-
MMBtu
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $310 $240 $310
4,689
kWh
-
TOTAL RECOMMENDED $11,880 $24,060 $9,490
179,366
kWh
$2,390
-
MMBtu
TOTAL IMPLEMENTED $9,490 $22,350 $9,490
179,366
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs