Assessment Year | 1994 |
---|---|
Principal Product | Asphalt |
NAICS |
n/a
|
SIC | 2951: Asphalt Paving Mixtures and Blocks |
Sales Range | $1 M to 5M |
# of Employees | 35 |
Plant Area |
2,400
ft2
|
Annual Production | 2,500,000
ton
|
Production Hrs. Annual | 3,588
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $238,730 | 4,807,444 |
kWh
|
$0.050 |
Natural Gas | $370,390 | 82,309 |
MMBtu
|
$4.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $32,310 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,700 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $12,900 | $5,430 | - |
$12,900
-
MMBtu
|
|
02 | 2.2136: Install / repair insulation on steam lines | $2,950 | $210 | - |
$2,950
-
MMBtu
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,810 | $300 |
$2,810
56,272
kWh
|
- | |
04 | 2.4133: Use most efficient type of electric motors | $7,810 | $24,740 |
$7,810
157,386
kWh
|
- | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,650 | $8,020 |
$2,650
53,341
kWh
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $430 | $850 |
$430
8,499
kWh
|
- | |
07 | 2.7111: Reduce illumination to minimum necessary levels | $2,760 | $1,800 |
$2,760
55,686
kWh
|
- | |
TOTAL RECOMMENDED | $32,310 | $41,350 |
$16,460
331,184
kWh
|
$15,850
-
MMBtu
|
||
TOTAL IMPLEMENTED | $13,700 | $33,910 |
$13,700
275,498
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs