ITAC Assessment: CO0292
ITAC logo
ITAC Assessment: CO0292
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Injection molded metal parts
NAICS
n/a
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 140
Plant Area 40,000
ft2
Annual Production 9,600,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $197,140 5,251,759
kWh
Natural Gas $2,290 389
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,290 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,780

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $2,990 $4,690 $2,990
79,719
kWh
- -
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,930 $2,400 - - $1,930
03 2.8121: Apply for tax-free status for energy purchases $1,860 $250 - - $1,860
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,630 $3,840 $1,630
43,376
kWh
- -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,150 $4,660 $1,150
30,481
kWh
- -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $910 $2,080 $910
24,326
kWh
- -
07 2.7261: Install timers and/or thermostats $460 $300 $290
19,930
kWh
$170
-
MMBtu
-
08 2.2511: Insulate bare equipment $360 $610 $360
8,499
kWh
- -
TOTAL RECOMMENDED $11,290 $18,830 $7,330
206,331
kWh
$170
-
MMBtu
$3,790
TOTAL IMPLEMENTED $9,780 $13,560 $5,820
167,351
kWh
$170
-
MMBtu
$3,790
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs