ITAC Assessment: CO0268
ITAC logo
ITAC Assessment: CO0268
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Baked Goods
NAICS
n/a
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $10
M
to 50
M
# of Employees 140
Plant Area 42,500
ft2
Annual Production 18,200,000
lb
Production Hrs. Annual 7,488
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $96,278 1,833,822
kWh
Natural Gas $43,641 15,812
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,280 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,350

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.8121: Apply for tax-free status for energy purchases $8,550 $250 - - $8,550
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,520 $420 $1,520
29,015
kWh
- -
03 2.7134: Use photocell controls $1,050 $1,000 $1,050
19,930
kWh
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,770 $1,000 $4,770
90,856
kWh
- -
05 2.4133: Use most efficient type of electric motors $930 $2,430 $930
17,585
kWh
- -
06 2.1233: Analyze flue gas for proper air/fuel ratio $460 $1,500 - $460
-
MMBtu
-
TOTAL RECOMMENDED $17,280 $6,600 $8,270
157,386
kWh
$460
-
MMBtu
$8,550
TOTAL IMPLEMENTED $16,350 $4,170 $7,340
139,801
kWh
$460
-
MMBtu
$8,550
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs