Assessment Year | 1992 |
---|---|
Principal Product | Packaged Tea |
NAICS |
n/a
|
SIC | 2099: Food Preparations, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
155,800
ft2
|
Annual Production | 3,200,000
pieces
|
Production Hrs. Annual | 5,425
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $178,375 | 3,041,325 |
kWh
|
$0.059 |
Natural Gas | $10,611 | 2,640 |
MMBtu
|
$4.02 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $20,500 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $20,500 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $5,300 | $250 | - | - | $5,300 | |
02 | 2.7224: Reduce space conditioning during non-working hours | $1,490 | $30 |
$800
31,067
kWh
|
$690
-
MMBtu
|
- | |
03 | 2.7314: Reduce ventilation air | $1,270 | $200 |
$140
2,345
kWh
|
$1,130
-
MMBtu
|
- | |
04 | 2.2427: Use waste heat from hot flue gases to preheat incoming fluids | $1,430 | $1,000 | - |
$1,430
-
MMBtu
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,400 | $4,910 |
$1,400
69,754
kWh
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,350 | $12,990 |
$3,350
57,151
kWh
|
- | - | |
07 | 2.4133: Use most efficient type of electric motors | $4,240 | $7,670 |
$4,240
72,392
kWh
|
- | - | |
08 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,020 | $6,500 | - | - | $2,020 | |
TOTAL RECOMMENDED | $20,500 | $33,550 |
$9,930
232,709
kWh
|
$3,250
-
MMBtu
|
$7,320 | ||
TOTAL IMPLEMENTED | $20,500 | $33,550 |
$9,930
232,709
kWh
|
$3,250
-
MMBtu
|
$7,320 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs