ITAC Assessment: CO0230
ITAC logo
ITAC Assessment: CO0230
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product CAN MANUFACTURING EQUIPMENT
NAICS
n/a
SIC 3542: Machine Tools, Metal Forming Types
Sales Range $1
M
to 5
M
# of Employees 45
Plant Area
n/a
Annual Production 25,000
lb
Production Hrs. Annual 2,860
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $45,164 596,424
kWh
Natural Gas $9,028 2,249
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,870 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,870

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.8121: Apply for tax-free status for energy purchases $1,520 $250 $1,309
-
kWh
$211
-
MMBtu
-
02 2.7224: Reduce space conditioning during non-working hours $2,070 $2,100 $440
16,706
kWh
$1,630
-
MMBtu
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $270 - $490
6,448
kWh
- $(-220.0)
04 2.7142: Utilize higher efficiency lamps and/or ballasts $490 $340 $490
6,448
kWh
- -
05 2.7134: Use photocell controls $280 $690 - $280
-
MMBtu
-
06 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system $2,240 $10,970 $2,240
86,166
kWh
- -
TOTAL RECOMMENDED $6,870 $14,350 $4,969
115,768
kWh
$2,121
-
MMBtu
$(-220.0)
TOTAL IMPLEMENTED $6,870 $14,350 $4,969
115,768
kWh
$2,121
-
MMBtu
$(-220.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs