| Assessment Year | 1990 |
|---|---|
| Principal Product | SCREWDRIVERS |
| NAICS |
n/a
|
| SIC | 3423: Hand and Edge Tools, Except Machine Tools and Handsaws |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
n/a
|
| Annual Production | 34,500,000
pieces
|
| Production Hrs. Annual | 6,816
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $143,387 | 3,274,619 |
kWh
|
$0.044 |
| Natural Gas | $40,964 | 10,792 |
MMBtu
|
$3.80 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $32,858 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,558 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $25,900 | $28,000 |
$25,900
-
kWh
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,300 | $1,000 |
$3,300
76,202
kWh
|
- | |
| 03 | 2.4133: Use most efficient type of electric motors | $850 | $1,630 |
$850
19,343
kWh
|
- | |
| 04 | 2.8211: Consolidate freight shipments and/or deliveries | $400 | $2,000 |
$1,050
-
kWh
|
$(-650.0) | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,825 | $1,606 |
$1,825
41,618
kWh
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $583 | $792 |
$583
13,189
kWh
|
- | |
| TOTAL RECOMMENDED | $32,858 | $35,028 |
$33,508
150,352
kWh
|
$(-650.0) | ||
| TOTAL IMPLEMENTED | $6,558 | $5,028 |
$6,558
150,352
kWh
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs