ITAC Assessment: CO0176
ITAC logo
ITAC Assessment: CO0176
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product FIRE PROOFING PRODUCTS
NAICS
n/a
SIC 3297: Nonclay Refractories
Sales Range $10
M
to 50
M
# of Employees 13
Plant Area
n/a
Annual Production 8,000,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $103,595 2,695,487
kWh
Natural Gas $170,705 59,267
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $58,518 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $47,998

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 3.4157: Replace water cooling on processes with air cooling $44,728 $40,000 $6,948
181,125
kWh
- $37,780
02 2.2414: Use waste heat from hot flue gases to preheat $9,130 $11,740 - $9,130
-
MMBtu
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,650 $1,000 $1,650
43,083
kWh
- -
04 2.4221: Install compressor air intakes in coolest locations $1,390 $500 $1,390
36,049
kWh
- -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,350 $1,800 $1,350
35,170
kWh
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $270 $200 $270
7,034
kWh
- -
TOTAL RECOMMENDED $58,518 $55,240 $11,608
302,461
kWh
$9,130
-
MMBtu
$37,780
TOTAL IMPLEMENTED $47,998 $43,000 $10,218
266,412
kWh
- $37,780
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs