| Assessment Year | 1990 |
|---|---|
| Principal Product | FIRE PROOFING PRODUCTS |
| NAICS |
n/a
|
| SIC | 3297: Nonclay Refractories |
| Sales Range | $10 M to 50M |
| # of Employees | 13 |
| Plant Area |
n/a
|
| Annual Production | 8,000,000
lb
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $103,595 | 2,695,487 |
kWh
|
$0.038 |
| Natural Gas | $170,705 | 59,267 |
MMBtu
|
$2.88 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $58,518 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $47,998 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 3.4157: Replace water cooling on processes with air cooling | $44,728 | $40,000 |
$6,948
181,125
kWh
|
- | $37,780 | |
| 02 | 2.2414: Use waste heat from hot flue gases to preheat | $9,130 | $11,740 | - |
$9,130
-
MMBtu
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,650 | $1,000 |
$1,650
43,083
kWh
|
- | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $1,390 | $500 |
$1,390
36,049
kWh
|
- | - | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,350 | $1,800 |
$1,350
35,170
kWh
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $270 | $200 |
$270
7,034
kWh
|
- | - | |
| TOTAL RECOMMENDED | $58,518 | $55,240 |
$11,608
302,461
kWh
|
$9,130
-
MMBtu
|
$37,780 | ||
| TOTAL IMPLEMENTED | $47,998 | $43,000 |
$10,218
266,412
kWh
|
- | $37,780 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs