| Assessment Year | 1986 |
|---|---|
| Principal Product | CONCRETE, ASPHALT, SAND |
| NAICS |
n/a
|
| SIC | 3272: Concrete Products, Except Block and Brick |
| Sales Range | $5 M to 10M |
| # of Employees | 40 |
| Plant Area |
n/a
|
| Annual Production | 150,000
ton
|
| Production Hrs. Annual | 2,340
hrs
|
| Location (State) | Wyoming |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $99,133 | 1,051,876 |
kWh
|
$0.094 |
| Natural Gas | $87,295 | 15,453 |
MMBtu
|
$5.65 |
| Fuel Oil #2 | $83,003 | 22,785 |
MMBtu
|
$3.64 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,904 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $15,588 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $6,351 | $200 | - |
$6,351
-
MMBtu
|
- | |
| 02 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,685 | $300 |
$1,685
17,878
kWh
|
- | - | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,132 | - |
$1,132
12,016
kWh
|
- | - | |
| 04 | 2.2427: Use waste heat from hot flue gases to preheat incoming fluids | $4,887 | $15,000 | - |
$4,887
-
MMBtu
|
- | |
| 05 | 2.3212: Optimize plant power factor | $1,533 | $3,931 |
$1,533
-
kWh
|
- | - | |
| 06 | 2.8223: Add air shields to trucks to increase fuel mileage | $3,316 | - | - | - |
$3,316
-
MMBtu
|
|
| TOTAL RECOMMENDED | $18,904 | $19,431 |
$4,350
29,894
kWh
|
$11,238
-
MMBtu
|
$3,316
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $15,588 | $19,431 |
$4,350
29,894
kWh
|
$11,238
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs