ITAC Assessment: CO0022
ITAC logo
ITAC Assessment: CO0022
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product PLEXIGLASS SKYLIGHTS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 70
Plant Area
n/a
Annual Production 1,100,000
pieces
Production Hrs. Annual 2,470
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $48,048 454,865
kWh
Natural Gas $25,956 5,145
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,408 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,354

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,005 $812 $3,005
28,429
kWh
- -
02 2.1233: Analyze flue gas for proper air/fuel ratio $235 $300 - $235
-
MMBtu
-
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $3,655 $5,000 $3,655
-
kWh
- -
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,408 $2,500 $1,766
16,706
kWh
$(-358.0)
-
MMBtu
-
05 2.1135: Repair furnaces and oven doors so that they seal efficiently $111 $100 - $111
-
MMBtu
-
06 2.6212: Turn off equipment during breaks, reduce operating time $1,775 $100 $1,775
16,706
kWh
- -
07 2.7243: Improve air circulation with destratification fans / other methods $1,991 $4,000 - $1,991
-
MMBtu
-
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $898 $100 $898
8,499
kWh
- -
09 2.6212: Turn off equipment during breaks, reduce operating time $253 $12 $31
293
kWh
$222
-
MMBtu
-
10 2.6214: Shut off pilots in standby equipment $77 - - $237
-
MMBtu
$(-160.0)
TOTAL RECOMMENDED $13,408 $12,924 $11,130
70,633
kWh
$2,438
-
MMBtu
$(-160.0)
TOTAL IMPLEMENTED $6,354 $1,424 $5,709
53,927
kWh
$805
-
MMBtu
$(-160.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs