Assessment Year | 1985 |
---|---|
Principal Product | PLEXIGLASS SKYLIGHTS |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 70 |
Plant Area |
n/a
|
Annual Production | 1,100,000
pieces
|
Production Hrs. Annual | 2,470
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $48,048 | 454,865 |
kWh
|
$0.11 |
Natural Gas | $25,956 | 5,145 |
MMBtu
|
$5.04 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,408 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,354 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,005 | $812 |
$3,005
28,429
kWh
|
- | - | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $235 | $300 | - |
$235
-
MMBtu
|
- | |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,655 | $5,000 |
$3,655
-
kWh
|
- | - | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,408 | $2,500 |
$1,766
16,706
kWh
|
$(-358.0)
-
MMBtu
|
- | |
05 | 2.1135: Repair furnaces and oven doors so that they seal efficiently | $111 | $100 | - |
$111
-
MMBtu
|
- | |
06 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,775 | $100 |
$1,775
16,706
kWh
|
- | - | |
07 | 2.7243: Improve air circulation with destratification fans / other methods | $1,991 | $4,000 | - |
$1,991
-
MMBtu
|
- | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $898 | $100 |
$898
8,499
kWh
|
- | - | |
09 | 2.6212: Turn off equipment during breaks, reduce operating time | $253 | $12 |
$31
293
kWh
|
$222
-
MMBtu
|
- | |
10 | 2.6214: Shut off pilots in standby equipment | $77 | - | - |
$237
-
MMBtu
|
$(-160.0) | |
TOTAL RECOMMENDED | $13,408 | $12,924 |
$11,130
70,633
kWh
|
$2,438
-
MMBtu
|
$(-160.0) | ||
TOTAL IMPLEMENTED | $6,354 | $1,424 |
$5,709
53,927
kWh
|
$805
-
MMBtu
|
$(-160.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs