| Assessment Year | 2022 |
|---|---|
| Principal Product | Frozen Food Storage |
| NAICS | 493120: Refrigerated Warehousing and Storage |
| SIC | 4222: Refrigerated Warehousing and Storage |
| Sales Range | $10 M to 50M |
| # of Employees | 55 |
| Plant Area |
140,000
ft2
|
| Annual Production | 2,000
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $192,200 | 4,362,000 |
kWh
|
$0.044 | |
| Electricity Demand | $63,650 | 8,216 |
kW-mo/yr
|
$7.75 | |
| Electricity Fees | $34,920 | - |
|
- | |
| Natural Gas | $46,573 | 11,940 |
MMBtu
|
$3.90 | |
| Waste Disposal Costs | |||||
| Water Usage | $1,731 | 528 |
Tgal
|
$3.28 | |
| Water Disposal | $5,295 | 919 |
Tgal
|
$5.76 | |
| TOTAL YEARLY COSTS | $344,369 | ||||
| RECOMMENDED SAVINGS* | $110,290 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $31,640 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7447: Install vinyl strip / high speed / air curtain doors | $21,300 | $72,000 |
$21,300
484,000
kWh
|
- | - | |
| 02 | 2.9114: Use solar heat to make electricty | $20,500 | $500,000 |
$8,900
203,000
kWh
|
$11,600
-
kW-mo/yr
|
- | |
| 03 | 2.4133: Use most efficient type of electric motors | $2,490 | $4,850 |
$1,980
44,880
kWh
|
$510
-
kW-mo/yr
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,250 | $11,350 |
$1,600
36,000
kWh
|
$650
-
kW-mo/yr
|
- | |
| 05 | 2.3113: Make ice during off peak hours for cooling | $10,340 | $57,600 | - |
$10,340
-
kW-mo/yr
|
- | |
| 06 | 2.3141: Use battery storage for demand control | $36,190 | $195,000 |
$3,850
87,240
kWh
|
$940
-
kW-mo/yr
|
$31,400 | |
| 07 | 4.812: Apply for investment incentives | $17,220 | $8,000 | - | - | $17,220 | |
| TOTAL RECOMMENDED | $110,290 | $848,800 |
$37,630
855,120
kWh
|
$24,040
-
kW-mo/yr
|
$48,620 | ||
| TOTAL IMPLEMENTED | $31,640 | $129,600 |
$21,300
484,000
kWh
|
$10,340
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs