| Assessment Year | 2022 |
|---|---|
| Principal Product | Educational Services |
| NAICS | 611210: Junior Colleges |
| SIC | 8222: Junior Colleges and Technical Institutes |
| Sales Range | $1 M to 5M |
| # of Employees | 424 |
| Plant Area |
100,000
ft2
|
| Annual Production | 2,000
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $220,982 | 5,181,696 |
kWh
|
$0.043 | |
| Electricity Demand | $171,386 | 9,558 |
kW-mo/yr
|
$17.93 | |
| Electricity Fees | $4,152 | - |
|
- | |
| Natural Gas | $102,780 | 16,800 |
MMBtu
|
$6.12 | |
| Waste Disposal Costs | |||||
| Water Usage | $64,649 | 11,203 |
Tgal
|
$5.77 | |
| TOTAL YEARLY COSTS | $563,949 | ||||
| RECOMMENDED SAVINGS* | $73,233 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $33,003 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,003 | $44,000 |
$6,729
160,300
kWh
|
$5,274
-
kW-mo/yr
|
- | |
| 02 | 2.7493: Use double or triple glazed windows to maintain higher relative humidity and to reduce heat losses | $1,800 | $100,000 |
$600
15,800
kWh
|
$700
-
kW-mo/yr
|
$500
-
MMBtu
|
|
| 03 | 2.4133: Use most efficient type of electric motors | $410 | $4,100 |
$240
5,500
kWh
|
$170
-
kW-mo/yr
|
- | |
| 04 | 2.1133: Adjust burners for efficient operation | $4,300 | $3,000 | - | - |
$4,300
-
MMBtu
|
|
| 05 | 2.7314: Reduce ventilation air | $21,000 | $740,000 |
$9,000
324,000
kWh
|
$12,000
-
kW-mo/yr
|
- | |
| 06 | 2.9114: Use solar heat to make electricty | $32,600 | $850,000 |
$32,600
358,000
kWh
|
- | - | |
| 07 | 2.6212: Turn off equipment during breaks, reduce operating time | $220 | $860 |
$220
6,800
kWh
|
- | - | |
| 08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $900 | $1,200 |
$500
14,000
kWh
|
$400
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $73,233 | $1,743,160 |
$49,889
884,400
kWh
|
$18,544
-
kW-mo/yr
|
$4,800
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $33,003 | $784,000 |
$15,729
484,300
kWh
|
$17,274
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs