Assessment Year | 1999 |
---|---|
Principal Product | Transformers, switchgear |
NAICS |
n/a
|
SIC | 3612: Power, Distribution, and Specialty Transformers |
Sales Range | $10 M to 50M |
# of Employees | 55 |
Plant Area |
50,000
ft2
|
Annual Production | 470
pieces
|
Production Hrs. Annual | 6,040
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $49,650 | 1,221,278 |
kWh
|
$0.041 |
Electricity Demand | $25,186 | 3,515 |
kW-mo/yr
|
$7.17 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $55,735 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $50,195 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $49,500 | $21,000 |
$16,000
694,607
kWh
|
$15,900
-
kW-mo/yr
|
$17,600
-
MMBtu
|
- | - | - | |
02 | 4.211: Consider use / purchase of bulk materials where possible | $4,830 | $75 | - | - | - | - | - | $4,830 | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $380 | $360 |
$60
2,638
kWh
|
$50
-
kW-mo/yr
|
- | - | $270 | - | |
04 | 2.7124: Make a practice of turning off lights when not needed | $315 | $35 |
$115
4,982
kWh
|
$200
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $300 | $500 |
$300
12,896
kWh
|
- | - | - | - | - | |
06 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $240 | $400 | - | - | - |
$240
-
lb
|
- | - | |
07 | 2.7124: Make a practice of turning off lights when not needed | $170 | - |
$170
7,327
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $55,735 | $22,370 |
$16,645
722,450
kWh
|
$16,150
-
kW-mo/yr
|
$17,600
-
MMBtu
|
$240
-
lb
|
$270 | $4,830 | ||
TOTAL IMPLEMENTED | $50,195 | $21,395 |
$16,175
702,227
kWh
|
$16,150
-
kW-mo/yr
|
$17,600
-
MMBtu
|
- | $270 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs