Assessment Year | 2021 |
---|---|
Principal Product | Fiberglass products, i.e. light poles, handles, cross arms |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3995: Burial Caskets |
Sales Range | $50 M to 100M |
# of Employees | 225 |
Plant Area |
250,000
ft2
|
Annual Production | 100,000,000
pieces
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | South Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $398,404 | 5,253,171 |
kWh
|
$0.076 | |
Electricity Demand | $206,131 | 12,883 |
kW-mo/yr
|
$16.00 | |
Electricity Fees | $1,289 | - |
|
- | |
Natural Gas | $115,236 | 1,301 |
MMBtu
|
$88.55 | |
Waste Disposal Costs | |||||
Water Usage | $7,742 | 102 |
Tgal
|
$75.90 | |
Water Disposal | $11,816 | 102 |
Tgal
|
$115.84 | |
TOTAL YEARLY COSTS | $740,618 | ||||
RECOMMENDED SAVINGS* | $46,904 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $46,904 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $34,650 | $33,470 |
$25,725
339,198
kWh
|
$8,925
-
kW-mo/yr
|
- | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,416 | $4,336 |
$1,088
14,349
kWh
|
$328
-
kW-mo/yr
|
- | |
03 | 2.2522: Isolate hot or cold equipment | $1,527 | $461 | - | - |
$1,527
-
MMBtu
|
|
04 | 2.4239: Eliminate or reduce compressed air usage | $9,311 | - |
$6,625
87,361
kWh
|
$2,686
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $46,904 | $38,267 |
$33,439
440,908
kWh
|
$11,939
-
kW-mo/yr
|
$1,527
-
MMBtu
|
||
TOTAL IMPLEMENTED | $46,904 | $38,267 |
$33,439
440,908
kWh
|
$11,939
-
kW-mo/yr
|
$1,527
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs