| Assessment Year | 2020 |
|---|---|
| Principal Product | High quality Potable Water |
| NAICS | 221310: Water Supply and Irrigation Systems |
| SIC | 4941: Water Supply |
| Sales Range | $50 M to 100M |
| # of Employees | 30 |
| Plant Area |
92,000
ft2
|
| Annual Production | 15,000,000
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | South Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $398,287 | 8,822,280 |
kWh
|
$0.045 | |
| Electricity Demand | $167,051 | 19,331 |
kW-mo/yr
|
$8.64 | |
| Electricity Fees | $2,909 | - |
|
- | |
| LPG | $60,000 | 12,000 |
MMBtu
|
$5.00 | |
| Waste Disposal Costs | |||||
| Water Usage | $1 | 50,000 |
Tgal
|
$0.000 | |
| Water Disposal | $1 | 50,000 |
Tgal
|
$0.000 | |
| Solid Waste (non-haz) | $20,000 | 100,000 |
lb
|
$0.20 | |
| TOTAL YEARLY COSTS | $648,249 | ||||
| RECOMMENDED SAVINGS* | $145,551 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $145,551 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,534 | $13,514 |
$11,594
256,810
kWh
|
$3,940
-
kW-mo/yr
|
- | |
| 02 | 2.7135: Install occupancy sensors | $1,084 | $656 |
$1,084
24,011
kWh
|
- | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $114,467 | $157,000 |
$61,614
1,364,795
kWh
|
$52,852
-
kW-mo/yr
|
- | |
| 04 | 4.463: Modify facility to avoid excess maintenance costs | $14,466 | $4,500 | - | - | $14,466 | |
| TOTAL RECOMMENDED | $145,551 | $175,670 |
$74,292
1,645,616
kWh
|
$56,792
-
kW-mo/yr
|
$14,466 | ||
| TOTAL IMPLEMENTED | $145,551 | $175,670 |
$74,292
1,645,616
kWh
|
$56,792
-
kW-mo/yr
|
$14,466 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs