| Assessment Year | 2019 |
|---|---|
| Principal Product | Treated waste water |
| NAICS | 562219: Other Nonhazardous Waste Treatment and Disposal |
| SIC | 4953: Refuse Systems |
| Sales Range | $1 M to 5M |
| # of Employees | 20 |
| Plant Area |
250,000
ft2
|
| Annual Production | 5,000
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | South Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $502,755 | 10,316,495 |
kWh
|
$0.049 | |
| Electricity Demand | $218,445 | 20,393 |
kW-mo/yr
|
$10.71 | |
| Electricity Fees | $1,126 | - |
|
- | |
| Natural Gas | $4,940 | 5,723 |
MMBtu
|
$0.86 | |
| Waste Disposal Costs | |||||
| Water Usage | $1,935 | 33 |
Tgal
|
$58.81 | |
| Water Disposal | $1 | 33 |
Tgal
|
$0.030 | |
| TOTAL YEARLY COSTS | $729,202 | ||||
| RECOMMENDED SAVINGS* | $126,298 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $126,298 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,753 | $16,667 |
$3,195
65,207
kWh
|
$3,558
-
kW-mo/yr
|
|
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $70,362 | $136,200 |
$54,149
1,105,074
kWh
|
$16,213
-
kW-mo/yr
|
|
| 03 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $49,183 | $300,000 |
$37,850
772,453
kWh
|
$11,333
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $126,298 | $452,867 |
$95,194
1,942,734
kWh
|
$31,104
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $126,298 | $452,867 |
$95,194
1,942,734
kWh
|
$31,104
-
kW-mo/yr
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs