Assessment Year | 2019 |
---|---|
Principal Product | Treated waste water |
NAICS | 562219: Other Nonhazardous Waste Treatment and Disposal |
SIC | 4953: Refuse Systems |
Sales Range | $1 M to 5M |
# of Employees | 20 |
Plant Area |
250,000
ft2
|
Annual Production | 5,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | South Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $502,755 | 10,316,495 |
kWh
|
$0.049 | |
Electricity Demand | $218,445 | 20,393 |
kW-mo/yr
|
$10.71 | |
Electricity Fees | $1,126 | - |
|
- | |
Natural Gas | $4,940 | 5,723 |
MMBtu
|
$0.86 | |
Waste Disposal Costs | |||||
Water Usage | $1,935 | 33 |
Tgal
|
$58.81 | |
Water Disposal | $1 | 33 |
Tgal
|
$0.030 | |
TOTAL YEARLY COSTS | $729,202 | ||||
RECOMMENDED SAVINGS* | $126,298 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $126,298 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,753 | $16,667 |
$3,195
65,207
kWh
|
$3,558
-
kW-mo/yr
|
|
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $70,362 | $136,200 |
$54,149
1,105,074
kWh
|
$16,213
-
kW-mo/yr
|
|
03 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $49,183 | $300,000 |
$37,850
772,453
kWh
|
$11,333
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $126,298 | $452,867 |
$95,194
1,942,734
kWh
|
$31,104
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $126,298 | $452,867 |
$95,194
1,942,734
kWh
|
$31,104
-
kW-mo/yr
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs