Assessment Year | 2019 |
---|---|
Principal Product | Clean Water |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $10 M to 50M |
# of Employees | 25 |
Plant Area |
25,000
ft2
|
Annual Production | 1,000,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | South Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $459,005 | 9,712,800 |
kWh
|
$0.047 | |
Electricity Demand | $216,118 | 17,664 |
kW-mo/yr
|
$12.23 | |
Electricity Fees | $1,020 | - |
|
- | |
Natural Gas | $22,681 | 1,983 |
MMBtu
|
$11.44 | |
Waste Disposal Costs | |||||
Water Usage | $6,017 | 152 |
Tgal
|
$39.72 | |
TOTAL YEARLY COSTS | $704,841 | ||||
RECOMMENDED SAVINGS* | $106,096 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $58,549 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $47,547 | $200,000 |
$35,111
742,304
kWh
|
$12,436
-
kW-mo/yr
|
|
02 | 2.5122: Replace high resistance ducts, pipes, and fittings | $15,899 | $5,500 |
$11,741
248,229
kWh
|
$4,158
-
kW-mo/yr
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $40,751 | $41,281 |
$23,827
506,946
kWh
|
$16,924
-
kW-mo/yr
|
|
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,899 | - |
$1,400
29,784
kWh
|
$499
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $106,096 | $246,781 |
$72,079
1,527,263
kWh
|
$34,017
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $58,549 | $46,781 |
$36,968
784,959
kWh
|
$21,581
-
kW-mo/yr
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs