Assessment Year | 2019 |
---|---|
Principal Product | API )Active Phamaceutical Ingredients) |
NAICS | 325412: Pharmaceutical Preparation Manufacturing |
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $10 M to 50M |
# of Employees | 125 |
Plant Area |
72,650
ft2
|
Annual Production | 22,000
lb
|
Production Hrs. Annual | 4,500
hrs
|
Location (State) | South Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $344,751 | 7,807,814 |
kWh
|
$0.044 | |
Electricity Demand | $185,264 | 16,924 |
kW-mo/yr
|
$10.95 | |
Electricity Fees | $7,049 | - |
|
- | |
Natural Gas | $211,378 | 34,398 |
MMBtu
|
$6.15 | |
Other Energy | $3,542 | 430 |
MMBtu
|
$8.24 | |
Waste Disposal Costs | |||||
Water Usage | $1,299 | 5,148 |
Tgal
|
$0.25 | |
Water Disposal | $11,375 | 5,148 |
Tgal
|
$2.21 | |
Other Liquid (haz) | $1,089,000 | 89,650 |
gal
|
$12.15 | |
TOTAL YEARLY COSTS | $1,853,658 | ||||
RECOMMENDED SAVINGS* | $167,881 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $7,160 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Energy Savings | Other Liquid (haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $17,417 | $15,294 |
$12,249
278,385
kWh
|
$5,168
-
kW-mo/yr
|
- | - | - | |
02 | 2.2135: Repair and eliminate steam leaks | $3,542 | $2,040 | - | - |
$3,542
-
MMBtu
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $647 | $2,080 |
$389
8,842
kWh
|
$258
-
kW-mo/yr
|
- | - | - | |
04 | 4.821: Pay bills on time to avoid late fees | $2,971 | - | - | - | - | - | $2,971 | |
05 | 3.6192: Use a less expensive method of waste removal | $143,304 | $600 | - | - | - |
$143,304
-
gal
|
- | |
TOTAL RECOMMENDED | $167,881 | $20,014 |
$12,638
287,227
kWh
|
$5,426
-
kW-mo/yr
|
$3,542
-
MMBtu
|
$143,304
-
gal
|
$2,971 | ||
TOTAL IMPLEMENTED | $7,160 | $4,120 |
$389
8,842
kWh
|
$258
-
kW-mo/yr
|
$3,542
-
MMBtu
|
- | $2,971 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs