| Assessment Year | 2026 |
|---|---|
| Principal Product | Lodging and Hospitality Services |
| NAICS | 721110: Hotels (except Casino Hotels) and Motels |
| SIC | 7011: Hotels and Motels |
| Sales Range | $10 M to 50M |
| # of Employees | 192 |
| Plant Area |
214,247
ft2
|
| Annual Production | 1,000
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $585,925 | 2,983,161 |
kWh
|
$0.20 |
| Electricity Demand | $71,815 | 7,824 |
kW-mo/yr
|
$9.18 |
| Electricity Fees | $129,923 | - |
|
- |
| TOTAL YEARLY COSTS | $787,663 | |||
| RECOMMENDED SAVINGS* | $343,084 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $102,497 | $989,315 |
$88,132
440,662
kWh
|
$14,365
-
kW-mo/yr
|
|
| 02 | 2.7135: Install occupancy sensors | $83,750 | $35,600 |
$80,525
410,004
kWh
|
$3,225
-
kW-mo/yr
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $46,578 | $22,000 |
$41,291
210,240
kWh
|
$5,287
-
kW-mo/yr
|
|
| 04 | 2.7212: Install or upgrade insulation on hvac distribution systems | $46,358 | $300,000 |
$46,358
236,039
kWh
|
- | |
| 05 | 2.4322: Use or replace with energy efficient substitutes | $26,270 | $77,000 |
$26,270
133,760
kWh
|
- | |
| 06 | 2.4322: Use or replace with energy efficient substitutes | $6,885 | $47,880 |
$2,204
44,077
kWh
|
$4,681
-
kW-mo/yr
|
|
| 07 | 2.4133: Use most efficient type of electric motors | $5,277 | $1,060 |
$4,959
25,289
kWh
|
$318
-
kW-mo/yr
|
|
| 08 | 2.7316: Centralize control of exhaust fans to ensure their shutdown, or establish program to ensure manual shutdown | $25,469 | $19,350 |
$24,542
9,776
kWh
|
$927
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $343,084 | $1,492,205 |
$314,281
1,509,847
kWh
|
$28,803
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs