ITAC Assessment: CI0085
ITAC logo
ITAC Assessment: CI0085
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Prepared Food
NAICS 722511: Full-Service Restaurants
SIC 5812: Eating Places
Sales Range $1
M
to 5
M
# of Employees 30
Plant Area 5,400
ft2
Annual Production 80,000
units
Production Hrs. Annual 4,368
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $22,316 111,080
kWh
Electricity Demand $9,370 726
kW-mo/yr
Electricity Fees $4,696 -
Natural Gas $20,000 4,000
MMBtu
Waste Disposal Costs
Water Usage $7,011 500
Tgal
Water Disposal $5,199 500
Tgal
TOTAL YEARLY COSTS $68,592
RECOMMENDED SAVINGS* $18,689 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4322: Use or replace with energy efficient substitutes $9,702 $21,100 $8,328
41,640
kWh
$1,374
-
kW-mo/yr
-
02 2.9114: Use solar heat to make electricty $4,674 $19,558 $4,349
21,746
kWh
$325
-
kW-mo/yr
-
03 2.1321: Replace fossil fuel equipment with electrical equipment $1,638 $3,000 - - $1,638
-
MMBtu
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,342 $693 $1,342
6,714
kWh
- -
05 2.7232: Replace existing hvac unit with high efficiency model $1,333 $7,500 $1,333
6,665
kWh
- -
TOTAL RECOMMENDED $18,689 $51,851 $15,352
76,765
kWh
$1,699
-
kW-mo/yr
$1,638
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs