| Assessment Year | 2026 |
|---|---|
| Principal Product | Gears and Power Transmission |
| NAICS | 333612: Speed Changer, Industrial High-Speed Drive, and Gear Manufacturing |
| SIC | 3566: Speed Changers, Industrial High-Speed Drives, and Gears |
| Sales Range | $100 M to 500M |
| # of Employees | 99 |
| Plant Area |
180,000
ft2
|
| Annual Production | 100,000
units
|
| Production Hrs. Annual | 5,590
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $256,122 | 2,491,594 |
kWh
|
$0.10 |
| Electricity Demand | $258,743 | 6,600 |
kW-mo/yr
|
$39.20 |
| Electricity Fees | $66,675 | - |
|
- |
| Natural Gas | $4,971 | 304 |
MMBtu
|
$16.35 |
| LPG | $45,540 | 1,180 |
MMBtu
|
$38.59 |
| Other Gas | $921 | 1 |
MMBtu
|
$921.00 |
| TOTAL YEARLY COSTS | $632,972 | |||
| RECOMMENDED SAVINGS* | $345,485 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | LPG Savings | Other Liquid (non-haz) Savings | One-time Revenue or Avoided Cost Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.652: Replace existing equipment with more suitable substitutes | $230,000 | $1,000,000 | - | - | - | - | - | - | - | $230,000 | |
| 02 | 2.5125: Size air handling grills/ duct/s coils to minimize air resistance | $50,000 | $365,000 |
$24,000
233,463
kWh
|
- | - | - | - | - | $26,000 | - | |
| 03 | 2.8227: Adjust / maintain fork lift trucks for most efficient operation | $39,972 | $78,000 |
$(-3,592.0)
(-34,944)
kWh
|
$(-1,976.0)
-
kW-mo/yr
|
- | - |
$45,540
-
MMBtu
|
- | - | - | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $12,133 | $7,225 |
$3,552
34,549
kWh
|
$6,582
-
kW-mo/yr
|
- | - | - | - | $1,999 | - | |
| 05 | 2.7212: Install or upgrade insulation on hvac distribution systems | $5,763 | $30,000 |
$5,763
56,061
kWh
|
- | - | - | - | - | - | - | |
| 06 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $3,360 | $7,500 | - | - | - | - | - |
$3,360
-
gal
|
- | - | |
| 07 | 2.3212: Optimize plant power factor | $2,237 | $6,500 | - | - | $2,237 | - | - | - | - | - | |
| 08 | 2.1321: Replace fossil fuel equipment with electrical equipment | $2,020 | $7,000 |
$(-1,962.0)
(-18,993)
kWh
|
- | - |
$3,982
-
MMBtu
|
- | - | - | - | |
| TOTAL RECOMMENDED | $345,485 | $1,501,225 |
$27,761
270,136
kWh
|
$4,606
-
kW-mo/yr
|
$2,237 |
$3,982
-
MMBtu
|
$45,540
-
MMBtu
|
$3,360
-
gal
|
$27,999 | $230,000 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | LPG Savings | Other Liquid (non-haz) Savings | One-time Revenue or Avoided Cost Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs