ITAC Assessment: CI0068
ITAC logo
ITAC Assessment: CI0068
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Aerospace Fuel Systems
NAICS 336412: Aircraft Engine and Engine Parts Manufacturing
SIC 3724: Aircraft Engines and Engine Parts
Sales Range $100
M
to 500
M
# of Employees 160
Plant Area 149,273
ft2
Annual Production 10,000
units
Production Hrs. Annual 6,240
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $195,579 1,487,925
kWh
Electricity Demand $204,341 8,291
kW-mo/yr
Electricity Fees $13,353 -
LPG $6,240 190
MMBtu
Waste Disposal Costs
Water Usage $1,352 369
Tgal
Other Liquid (non-haz) $6,072 1
gal
TOTAL YEARLY COSTS $426,937
RECOMMENDED SAVINGS* $230,522 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings
01 2.9114: Use solar heat to make electricty $70,614 $464,950 $55,084
419,212
kWh
$15,530
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $65,080 $1,300 $52,944
402,932
kWh
$12,136
-
kW-mo/yr
-
03 2.3141: Use battery storage for demand control $28,645 $100,000 $13,115
99,813
kWh
$15,530
-
kW-mo/yr
-
04 2.4322: Use or replace with energy efficient substitutes $21,318 $150,000 $21,318
81,120
kWh
- -
05 2.4239: Eliminate or reduce compressed air usage $15,432 - $15,432
117,429
kWh
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $12,379 $15,000 $4,364
33,216
kWh
$8,015
-
kW-mo/yr
-
07 2.3132: Recharge batteries on during off-peak demand periods $7,987 $200 - $7,987
-
kW-mo/yr
-
08 2.7135: Install occupancy sensors $4,821 $4,000 $4,821
36,691
kWh
- -
09 2.8227: Adjust / maintain fork lift trucks for most efficient operation $4,246 $16,000 $(-1,039.0)
(-7,904)
kWh
$(-955.0)
-
kW-mo/yr
$6,240
-
MMBtu
TOTAL RECOMMENDED $230,522 $751,450 $166,039
1,182,509
kWh
$58,243
-
kW-mo/yr
$6,240
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs