ITAC Assessment: CI0064
ITAC logo
ITAC Assessment: CI0064
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Office Building
NAICS 531210: Offices of Real Estate Agents and Brokers
SIC 6531: Real Estate Agents and Managers
Sales Range $1
M
to 5
M
# of Employees 7
Plant Area 80,000
ft2
Annual Production 1
units
Production Hrs. Annual 2,340
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $180,170 1,136,155
kWh
Electricity Demand $68,676 3,230
kW-mo/yr
Electricity Fees $37,118 -
TOTAL YEARLY COSTS $285,964
RECOMMENDED SAVINGS* $92,306 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.9114: Use solar heat to make electricty $56,021 $378,965 $45,109
284,421
kWh
$10,912
-
kW-mo/yr
02 2.7142: Utilize higher efficiency lamps and/or ballasts $11,886 $7,876 $2,720
17,148
kWh
$9,166
-
kW-mo/yr
03 2.1224: Replace boiler $9,932 $40,000 $9,932
62,626
kWh
-
04 2.7316: Centralize control of exhaust fans to ensure their shutdown, or establish program to ensure manual shutdown $6,768 $500 $5,697
35,920
kWh
$1,071
-
kW-mo/yr
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,090 $1,100 $2,527
15,938
kWh
$1,563
-
kW-mo/yr
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,065 $6,000 $1,215
7,662
kWh
$850
-
kW-mo/yr
07 2.4226: Use / purchase optimum sized compressor $1,544 $12,000 $1,544
5,237
kWh
-
TOTAL RECOMMENDED $92,306 $446,441 $68,744
428,952
kWh
$23,562
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs