Assessment Year | 2025 |
---|---|
Principal Product | Tortilla Chips, Taco Shells & Pellet Snacks |
NAICS | 311919: Other Snack Food Manufacturing |
SIC | 2096: Potato Chips, Corn Chips, and Similar Snacks |
Sales Range | $50 M to 100M |
# of Employees | 230 |
Plant Area |
133,665
ft2
|
Annual Production | 30,000,000
lb
|
Production Hrs. Annual | 6,600
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $809,513 | 3,557,422 |
kWh
|
$0.23 | |
Electricity Demand | $233,366 | 17,164 |
kW-mo/yr
|
$13.60 | |
Electricity Fees | $59,426 | - |
|
- | |
Natural Gas | $1,583,938 | 105,280 |
MMBtu
|
$15.05 | |
Other Gas | $101,940 | 1 |
MMBtu
|
$101,940.00 | |
Waste Disposal Costs | |||||
Water Usage | $276,674 | 9,180 |
Tgal
|
$30.14 | |
TOTAL YEARLY COSTS | $3,064,857 | ||||
RECOMMENDED SAVINGS* | $794,604 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.1321: Replace fossil fuel equipment with electrical equipment | $316,788 | $3,200,000 | - | - |
$316,788
-
MMBtu
|
|
02 | 2.9114: Use solar heat to make electricty | $138,402 | $619,600 |
$126,978
557,900
kWh
|
$11,424
-
kW-mo/yr
|
- | |
03 | 2.2442: Preheat combustion air with waste heat | $127,862 | $20,000 |
$118,122
518,991
kWh
|
$9,740
-
kW-mo/yr
|
- | |
04 | 2.2515: Use optimum thickness insulation | $67,904 | $174,000 |
$67,904
298,346
kWh
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $57,280 | $7,800 |
$51,862
227,864
kWh
|
$5,418
-
kW-mo/yr
|
- | |
06 | 2.4133: Use most efficient type of electric motors | $26,465 | $20,000 |
$23,821
104,662
kWh
|
$2,644
-
kW-mo/yr
|
- | |
07 | 2.3141: Use battery storage for demand control | $20,703 | $50,000 |
$19,071
93,100
kWh
|
$1,632
-
kW-mo/yr
|
- | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $17,542 | $3,762 |
$13,640
59,928
kWh
|
$3,902
-
kW-mo/yr
|
- | |
09 | 2.7134: Use photocell controls | $14,804 | $4,000 |
$10,897
47,880
kWh
|
$3,907
-
kW-mo/yr
|
- | |
10 | 2.3132: Recharge batteries on during off-peak demand periods | $6,854 | $200 | - |
$6,854
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $794,604 | $4,099,362 |
$432,295
1,908,671
kWh
|
$45,521
-
kW-mo/yr
|
$316,788
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs