| Assessment Year | 2023 |
|---|---|
| Principal Product | Grain Based Breakfast Cereals |
| NAICS | 311230: Breakfast Cereal Manufacturing |
| SIC | 2043: Cereal Breakfast Foods |
| Sales Range | $10 M to 50M |
| # of Employees | 60 |
| Plant Area |
200,000
ft2
|
| Annual Production | 12,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $210,344 | 1,517,486 |
kWh
|
$0.14 | |
| Electricity Demand | $31,474 | 4,662 |
kW-mo/yr
|
$6.75 | |
| Electricity Fees | $118,730 | - |
|
- | |
| Natural Gas | $115,991 | 11,599 |
MMBtu
|
$10.00 | |
| Waste Disposal Costs | |||||
| Water Usage | $9,428 | 5,830 |
Tgal
|
$1.62 | |
| Water Disposal | $1,269 | 5,830 |
Tgal
|
$0.22 | |
| TOTAL YEARLY COSTS | $487,236 | ||||
| RECOMMENDED SAVINGS* | $171,403 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $78,738 | $658,288 |
$72,614
523,908
kWh
|
$6,124
-
kW-mo/yr
|
- | - | |
| 02 | 2.2511: Insulate bare equipment | $45,480 | $17,533 | - | - |
$45,480
-
MMBtu
|
- | |
| 03 | 2.1224: Replace boiler | $13,894 | $30,000 |
$(-29,059.0)
(-209,664)
kWh
|
$(-545.0)
-
kW-mo/yr
|
$43,498
-
MMBtu
|
- | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,902 | $300 |
$7,226
52,136
kWh
|
$676
-
kW-mo/yr
|
- | - | |
| 05 | 2.7135: Install occupancy sensors | $7,791 | $2,625 |
$7,539
54,395
kWh
|
$252
-
kW-mo/yr
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,881 | $2,299 |
$5,424
39,137
kWh
|
$457
-
kW-mo/yr
|
- | - | |
| 07 | 2.3132: Recharge batteries on during off-peak demand periods | $5,670 | $7,500 | - |
$5,670
-
kW-mo/yr
|
- | - | |
| 08 | 2.2437: Recover waste heat from equipment | $3,797 | $5,000 |
$2,177
15,709
kWh
|
$1,620
-
kW-mo/yr
|
- | - | |
| 09 | 4.652: Replace existing equipment with more suitable substitutes | $2,250 | $13,000 | - | - | - | $2,250 | |
| TOTAL RECOMMENDED | $171,403 | $736,545 |
$65,921
475,621
kWh
|
$14,254
-
kW-mo/yr
|
$88,978
-
MMBtu
|
$2,250 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs