ITAC Assessment: CI0017
ITAC logo
ITAC Assessment: CI0017
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Packaged Food Products
NAICS 311991: Perishable Prepared Food Manufacturing
SIC 2099: Food Preparations, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 145
Plant Area 68,000
ft2
Annual Production 15,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $435,603 3,794,897
kWh
Electricity Demand $286,480 16,438
kW-mo/yr
Electricity Fees $32,462 -
Natural Gas $168,145 11,899
MMBtu
Waste Disposal Costs
Water Usage $27,593 5,800
Tgal
Water Disposal $2,629 5,800
Tgal
TOTAL YEARLY COSTS $952,912
RECOMMENDED SAVINGS* $414,731 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.9114: Use solar heat to make electricty $271,104 $1,391,144 $218,361
1,902,137
kWh
$52,743
-
kW-mo/yr
-
02 2.1321: Replace fossil fuel equipment with electrical equipment $63,711 $90,000 $(-90,508.0)
(-788,400)
kWh
$(-9,411.0)
-
kW-mo/yr
$163,630
-
MMBtu
03 2.1224: Replace boiler $25,947 $36,000 $(-45,053.0)
(-392,448)
kWh
$(-4,685.0)
-
kW-mo/yr
$75,685
-
MMBtu
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $21,971 $39,000 $21,507
187,342
kWh
$464
-
kW-mo/yr
-
05 2.3137: Use power during off-peak periods $12,483 $22,000 - $12,483
-
kW-mo/yr
-
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $11,433 $1,500 $9,429
82,134
kWh
$2,004
-
kW-mo/yr
-
07 2.4231: Reduce the pressure of compressed air to the minimum required $6,491 - $5,346
46,568
kWh
$1,145
-
kW-mo/yr
-
08 2.2442: Preheat combustion air with waste heat $1,591 $5,000 $964
8,394
kWh
$627
-
kW-mo/yr
-
TOTAL RECOMMENDED $414,731 $1,584,644 $120,046
1,045,727
kWh
$55,370
-
kW-mo/yr
$239,315
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs