ITAC Assessment: CI0011
ITAC logo
ITAC Assessment: CI0011
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Battery Manufacturing
NAICS 334515: Instrument Manufacturing for Measuring and Testing Electricity and Electrical Signals
SIC 3691: Storage Batteries
Sales Range $10
M
to 50
M
# of Employees 45
Plant Area 224,116
ft2
Annual Production 100,000
units
Production Hrs. Annual 2,210
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $82,002 115,676
kWh
Electricity Demand $15,036 2,482
kW-mo/yr
Natural Gas $26,535 970
MMBtu
Waste Disposal Costs
Water Usage $5,349 519
Tgal
Water Disposal $3,764 519
Tgal
TOTAL YEARLY COSTS $132,686
RECOMMENDED SAVINGS* $30,646 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7135: Install occupancy sensors $11,157 $4,800 $10,904
15,382
kWh
$253
-
kW-mo/yr
02 2.1321: Replace fossil fuel equipment with electrical equipment $8,809 $20,000 $8,809
12,426
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $4,448 $2,393 $4,430
6,249
kWh
$18
-
kW-mo/yr
04 2.6218: Turn off equipment when not in use $2,298 - $2,298
3,242
kWh
-
05 2.3132: Recharge batteries on during off-peak demand periods $2,181 $6,150 - $2,181
-
kW-mo/yr
06 2.4239: Eliminate or reduce compressed air usage $1,753 $500 $1,753
2,473
kWh
-
TOTAL RECOMMENDED $30,646 $33,843 $28,194
39,772
kWh
$2,452
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs