Assessment Year | 2022 |
---|---|
Principal Product | Residential Door Locks and Cabinet Hardware Accessories |
NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
SIC | 3429: Hardware, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 389 |
Plant Area |
218,600
ft2
|
Annual Production | 1,000,000
pieces
|
Production Hrs. Annual | 3,060
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $279,304 | 1,386,000 |
kWh
|
$0.20 | |
Natural Gas | $15,033 | 1,397 |
MMBtu
|
$10.76 | |
LPG | $38,508 | 1 |
MMBtu
|
$38,508.00 | |
Waste Disposal Costs | |||||
Water Usage | $1 | 1 |
Tgal
|
$0.83 | |
TOTAL YEARLY COSTS | $332,846 | ||||
RECOMMENDED SAVINGS* | $104,906 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.8227: Adjust / maintain fork lift trucks for most efficient operation | $33,479 | $80,000 | - |
$33,479
-
MMBtu
|
- | - | |
02 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $27,300 | $24,600 |
$27,300
135,486
kWh
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $18,201 | $1,800 |
$18,201
90,329
kWh
|
- | - | - | |
04 | 2.4239: Eliminate or reduce compressed air usage | $12,649 | $30,000 |
$12,649
62,776
kWh
|
- | - | - | |
05 | 2.4325: Upgrade conveyors | $3,825 | $8,040 | - | - | $3,825 | - | |
06 | 2.6218: Turn off equipment when not in use | $3,680 | - |
$3,680
18,262
kWh
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,733 | $2,167 |
$2,733
13,563
kWh
|
- | - | - | |
08 | 2.7135: Install occupancy sensors | $1,717 | $2,625 |
$1,717
8,520
kWh
|
- | - | - | |
09 | 2.7134: Use photocell controls | $1,322 | $1,350 |
$1,152
5,718
kWh
|
- | $77 | $93 | |
TOTAL RECOMMENDED | $104,906 | $150,582 |
$67,432
334,654
kWh
|
$33,479
-
MMBtu
|
$3,902 | $93 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | LPG Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs