| Assessment Year | 2024 |
|---|---|
| Principal Product | brominated flame retardants and plasticizers |
| NAICS | 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing |
| SIC | 2869: Industrial Organic Chemicals, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 50 |
| Plant Area |
70,000
ft2
|
| Annual Production | 30,000,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $227,536 | 3,710,594 |
kWh
|
$0.061 |
| Electricity Demand | $57,690 | 6,952 |
kW-mo/yr
|
$8.30 |
| Electricity Fees | $21,552 | - |
|
- |
| Natural Gas | $346,271 | 62,120 |
MMBtu
|
$5.57 |
| TOTAL YEARLY COSTS | $653,049 | |||
| RECOMMENDED SAVINGS* | $78,747 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $24,323 | $22,680 |
$20,440
335,088
kWh
|
$3,883
-
kW-mo/yr
|
- | |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $14,523 | $8,400 |
$13,001
213,138
kWh
|
$1,522
-
kW-mo/yr
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,159 | $1,880 |
$935
15,330
kWh
|
$224
-
kW-mo/yr
|
- | |
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $4,235 | - |
$3,570
58,517
kWh
|
$665
-
kW-mo/yr
|
- | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,282 | $1,000 |
$1,924
31,536
kWh
|
$358
-
kW-mo/yr
|
- | |
| 06 | 2.2437: Recover waste heat from equipment | $1,010 | $2,500 | - | - |
$1,010
-
MMBtu
|
|
| 07 | 2.4239: Eliminate or reduce compressed air usage | $11,158 | $17,000 |
$9,405
154,176
kWh
|
$1,753
-
kW-mo/yr
|
- | |
| 08 | 2.2121: Increase amount of condensate returned | $2,800 | - | - | - |
$2,800
-
MMBtu
|
|
| 09 | 2.9114: Use solar heat to make electricty | $17,257 | $183,891 |
$17,257
282,899
kWh
|
- | - | |
| TOTAL RECOMMENDED | $78,747 | $237,351 |
$66,532
1,090,684
kWh
|
$8,405
-
kW-mo/yr
|
$3,810
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs