Assessment Year | 2024 |
---|---|
Principal Product | Furniture Decking, Drapery Linings, Work Wear |
NAICS | 313310: Textile and Fabric Finishing Mills |
SIC | 2269: Finishers of Textiles, Not elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
350,000
ft2
|
Annual Production | 204,000
thousand feet
|
Production Hrs. Annual | 2,400
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $315,927 | 5,974,277 |
kWh
|
$0.053 |
Electricity Demand | $86,556 | 18,940 |
kW-mo/yr
|
$4.57 |
Electricity Fees | $705 | - |
|
- |
Natural Gas | $736,419 | 186,158 |
MMBtu
|
$3.96 |
TOTAL YEARLY COSTS | $1,139,607 | |||
RECOMMENDED SAVINGS* | $134,371 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2123: Insulate feedwater tank | $443 | $834 | - | - |
$443
-
MMBtu
|
|
02 | 2.2136: Install / repair insulation on steam lines | $620 | $3,033 | - | - |
$620
-
MMBtu
|
|
03 | 2.2444: Use hot process fluids to preheat incoming process fluids | $116,489 | $300,000 | - | - |
$116,489
-
MMBtu
|
|
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $452 | $966 |
$320
6,032
kWh
|
$133
-
kW-mo/yr
|
- | |
05 | 2.4226: Use / purchase optimum sized compressor | $15,374 | $77,000 |
$12,576
237,288
kWh
|
$2,798
-
kW-mo/yr
|
- | |
06 | 2.2135: Repair and eliminate steam leaks | $992 | $1,500 | - | - |
$992
-
MMBtu
|
|
TOTAL RECOMMENDED | $134,371 | $383,333 |
$12,896
243,319
kWh
|
$2,930
-
kW-mo/yr
|
$118,545
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs