ITAC Assessment: CC0026
ITAC logo
ITAC Assessment: CC0026
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Furniture Decking, Drapery Linings, Work Wear
NAICS 313310: Textile and Fabric Finishing Mills
SIC 2269: Finishers of Textiles, Not elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 350,000
ft2
Annual Production 204,000
thousand feet
Production Hrs. Annual 2,400
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $315,927 5,974,277
kWh
Electricity Demand $86,556 18,940
kW-mo/yr
Electricity Fees $705 -
Natural Gas $736,419 186,158
MMBtu
TOTAL YEARLY COSTS $1,139,607
RECOMMENDED SAVINGS* $134,371 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2123: Insulate feedwater tank $443 $834 - - $443
-
MMBtu
02 2.2136: Install / repair insulation on steam lines $620 $3,033 - - $620
-
MMBtu
03 2.2444: Use hot process fluids to preheat incoming process fluids $116,489 $300,000 - - $116,489
-
MMBtu
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $452 $966 $320
6,032
kWh
$133
-
kW-mo/yr
-
05 2.4226: Use / purchase optimum sized compressor $15,374 $77,000 $12,576
237,288
kWh
$2,798
-
kW-mo/yr
-
06 2.2135: Repair and eliminate steam leaks $992 $1,500 - - $992
-
MMBtu
TOTAL RECOMMENDED $134,371 $383,333 $12,896
243,319
kWh
$2,930
-
kW-mo/yr
$118,545
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs