ITAC Assessment: CC0021
ITAC logo
ITAC Assessment: CC0021
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product micro-optics; glass and silicon wafers
NAICS 333314: Optical Instrument and Lens Manufacturing
SIC 3827: Optical Instruments and Lenses
Sales Range $100
M
to 500
M
# of Employees 50
Plant Area 100,000
ft2
Annual Production 400,000
units
Production Hrs. Annual 8,760
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $461,066 12,304,652
kWh
Electricity Demand $240,747 24,969
kW-mo/yr
Electricity Fees $741 -
Natural Gas $133,637 12,714
MMBtu
TOTAL YEARLY COSTS $836,191
RECOMMENDED SAVINGS* $103,378 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $50,657 $5,000 $40,459
1,093,485
kWh
$10,198
-
kW-mo/yr
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $9,378 $25,947 $5,444
147,145
kWh
$3,934
-
kW-mo/yr
-
03 2.2437: Recover waste heat from equipment $12,396 $15,000 $(-186.4)
(-5,037)
kWh
$(-66.5)
-
kW-mo/yr
$12,649
-
MMBtu
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,174 - $4,550
122,970
kWh
$1,624
-
kW-mo/yr
-
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $12,085 $35,000 $8,906
240,705
kWh
$3,179
-
kW-mo/yr
-
06 2.4231: Reduce the pressure of compressed air to the minimum required $5,760 - $4,245
114,722
kWh
$1,515
-
kW-mo/yr
-
07 2.7241: Install outside air damper / economizer on hvac unit $6,928 $5,000 $6,928
187,250
kWh
- -
TOTAL RECOMMENDED $103,378 $85,947 $70,346
1,901,240
kWh
$20,384
-
kW-mo/yr
$12,649
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs