| Assessment Year | 2023 |
|---|---|
| Principal Product | Automotive Textile |
| NAICS | 336360: Motor Vehicle Seating and Interior Trim Manufacturing |
| SIC | 2399: Fabricated Textile Products, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 105 |
| Plant Area |
360,000
ft2
|
| Annual Production | 21,000
thousand feet
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | South Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $893,562 | 17,086,511 |
kWh
|
$0.052 |
| Electricity Demand | $178,296 | 37,608 |
kW-mo/yr
|
$4.74 |
| Electricity Fees | $1,611 | - |
|
- |
| TOTAL YEARLY COSTS | $1,073,469 | |||
| RECOMMENDED SAVINGS* | $246,420 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $90,004 | - |
$76,577
1,472,640
kWh
|
$13,427
-
kW-mo/yr
|
|
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,997 | $8,484 |
$3,371
64,833
kWh
|
$626
-
kW-mo/yr
|
|
| 03 | 2.6218: Turn off equipment when not in use | $6,445 | - |
$5,484
105,456
kWh
|
$961
-
kW-mo/yr
|
|
| 04 | 2.7135: Install occupancy sensors | $4,836 | $6,196 |
$4,113
79,092
kWh
|
$723
-
kW-mo/yr
|
|
| 05 | 2.7124: Make a practice of turning off lights when not needed | $1,525 | - |
$1,525
29,328
kWh
|
- | |
| 06 | 2.9114: Use solar heat to make electricty | $139,613 | $1,192,963 |
$139,613
2,684,865
kWh
|
- | |
| TOTAL RECOMMENDED | $246,420 | $1,207,643 |
$230,683
4,436,214
kWh
|
$15,737
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs