ITAC Assessment: CC0017
ITAC logo
ITAC Assessment: CC0017
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Automotive Textile
NAICS 336360: Motor Vehicle Seating and Interior Trim Manufacturing
SIC 2399: Fabricated Textile Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 105
Plant Area 360,000
ft2
Annual Production 21,000
thousand feet
Production Hrs. Annual 6,240
hrs
Location (State) South Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $893,562 17,086,511
kWh
Electricity Demand $178,296 37,608
kW-mo/yr
Electricity Fees $1,611 -
TOTAL YEARLY COSTS $1,073,469
RECOMMENDED SAVINGS* $246,420 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $90,004 - $76,577
1,472,640
kWh
$13,427
-
kW-mo/yr
02 2.7142: Utilize higher efficiency lamps and/or ballasts $3,997 $8,484 $3,371
64,833
kWh
$626
-
kW-mo/yr
03 2.6218: Turn off equipment when not in use $6,445 - $5,484
105,456
kWh
$961
-
kW-mo/yr
04 2.7135: Install occupancy sensors $4,836 $6,196 $4,113
79,092
kWh
$723
-
kW-mo/yr
05 2.7124: Make a practice of turning off lights when not needed $1,525 - $1,525
29,328
kWh
-
06 2.9114: Use solar heat to make electricty $139,613 $1,192,963 $139,613
2,684,865
kWh
-
TOTAL RECOMMENDED $246,420 $1,207,643 $230,683
4,436,214
kWh
$15,737
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs