ITAC Assessment: CC0008
ITAC logo
ITAC Assessment: CC0008
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Soft Drinks
NAICS 312111: Soft Drink Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $100
M
to 500
M
# of Employees 350
Plant Area 500,000
ft2
Annual Production 147,536
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $772,846 20,917,069
kWh
Electricity Demand $400,318 39,118
kW-mo/yr
Electricity Fees $2,193 -
Natural Gas $414,186 58,457
MMBtu
TOTAL YEARLY COSTS $1,589,543
RECOMMENDED SAVINGS* $215,855 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,632 $1,975 $3,359
90,782
kWh
$1,273
-
kW-mo/yr
-
02 2.1392: Replace purchased steam with other energy source $53,990 $140,000 - - $53,990
-
MMBtu
03 2.6242: Minimize operation of equipment maintained in standby condition $111,035 $52,000 $80,517
2,176,123
kWh
$30,518
-
kW-mo/yr
-
04 2.2611: Moderate cooling tower outlet temperature $3,081 - $3,081
83,277
kWh
- -
05 2.1221: Replace obsolete burners with more efficient ones $29,148 $60,000 - - $29,148
-
MMBtu
06 2.2511: Insulate bare equipment $1,403 $5,250 - - $1,403
-
MMBtu
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $8,938 $50,000 $6,482
175,200
kWh
$2,456
-
kW-mo/yr
-
08 2.7142: Utilize higher efficiency lamps and/or ballasts $3,628 $3,444 $2,265
61,219
kWh
$1,363
-
kW-mo/yr
-
TOTAL RECOMMENDED $215,855 $312,669 $95,704
2,586,601
kWh
$35,610
-
kW-mo/yr
$84,541
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs